Fangjiashan Nuclear Power Plant

Nuclear power plant in Zhejiang, China From Wikipedia, the free encyclopedia

Fangjiashan Nuclear Power Plant (方家山核电站) is a nuclear power plant in the Zhejiang province, China, bordering the Shanghai municipality. The plant consists of two 1,080 MW CPR-1000 pressurized water reactors (PWR) at a total cost of estimated 26 billion yuan (US$ 3.8 billion).[1]

Official name
  • 方家山核电站
CountryPeople's Republic of China
Coordinates30°26′29″N 120°56′30″E
Quick facts Official name, Country ...
Fangjiashan Nuclear Power Plant
Official name
  • 方家山核电站
CountryPeople's Republic of China
LocationZhejiang province
Coordinates30°26′29″N 120°56′30″E
StatusOperational
Construction began2008
Commission date2014
Construction cost26 billion yuan (US$3.8 billion)
OwnerChina National Nuclear Corporation (CNNC)
Operator
Nuclear power station
Reactor typeCPR-1000 PWR
Power generation
Units operational2 × 1012 MW
Nameplate capacity2024 MW
Annual net output15,152 GWh (2016)
Close

'First concrete' for the first unit at the Fangjiashan plant was poured on 26 December 2008, construction of the second unit followed in July 2009. Construction was done by China Nuclear Power Engineering (CNPE), while the reactor pressure vessels were manufactured by China First Heavy Industries and the turbosets by Dongfang Electric. The reactors were put in commercial operation in December 2014 and February 2015, respectively.[2][3]

The existing Qinshan Nuclear Power Plant with 7 reactors is nearby: essentially Fangjiashan NPP is an extension of the Qinshan NPP, forming an aggregated complex. The Fangjiashan NPP is mainly owned by CNNC (72%), with minority stakes by Zhejiang Provincial Energy Group Co Ltd.[4]

Two units of CNNC's CNP-1000 were due to be installed at Fangjiashan Nuclear Power Plant. However, the design was subsequently changed to CGN's CPR-1000.

Reactor data

The Fangjiashan Nuclear Power Plant consists of 2 operational reactors.[4]

More information Unit, Type ...
UnitTypeModelNet
power
Gross
power
Thermal
power
Construction
start
First
criticality
Grid
connection
Operation
start
Notes
Fangjiashan 1PWRCPR-10001012 MW1089 MW2905 MW2008-12-262014-10-212014-11-042014-12-15 [5]
Fangjiashan 2PWRCPR-10001012 MW1089 MW2905 MW2009-7-172014-10-212015-01-122015-02-12 [6]
Close

See also

References