Silver State South Solar Project

Photovoltaic power plant located in Clark County, Nevada, From Wikipedia, the free encyclopedia

The Silver State South Solar Project is a 250 megawatt (MWAC) photovoltaic power plant located in Clark County, Nevada, and near the previously completed 50 MWAC Silver State North Solar Project and the 530 MW gas-fired Higgins Generating Station. The project was completed in late 2016 and was constructed by subcontractors for First Solar.[1][2] The plant is owned and operated by a subsidiary of NextEra Energy Resources, and power is being sold to Southern California Edison.[3]

CountryUnited States
LocationClark County
Coordinates35°36′37″N 115°20′06″W
StatusOperational
Quick facts Country, Location ...
Silver State South Solar Project
CountryUnited States
LocationClark County
Coordinates35°36′37″N 115°20′06″W
StatusOperational
Construction beganSeptember 3, 2014
Commission dateDecember 9, 2016
OwnerNextEra Energy Resources
Solar farm
TypeFlat-panel PV
single-axis tracking
Site area2,900 acres (1,200 ha)
Power generation
Nameplate capacity250 MWAC
Capacity factor31.6% (average 2017-2019)
Annual net output692 GW·h, 239 MW·h/acre
Close
Layout of the project near Primm, NV

The project occupies approximately 2,900 acres of public lands[4] and is located adjacent to Primm, Nevada, in the Jean Lake/Roach Lake Special Recreation Management Area (SRMA).[5]

Electricity Production

More information Year, Jan ...
Generation (MW·h) of Silver State Solar Power South [6]
YearJanFebMarAprMayJunJulAugSepOctNovDecTotal
2015 3848,211 8,595
2016 13,53323,35129,16745,95662,92161,97166,96271,71863,43951,75639,47928,335 558,588
2017 29,55632,84856,69362,42169,85973,67771,27878,32873,82671,82546,78744,062 711,159
2018 33,72943,25655,40169,16473,14485,66272,96673,78370,97555,64343,49833,672 710,894
2019 34,52237,77452,25161,82465,52372,16872,87670,95960,66358,88840,18527,138 654,772