DND–KMP Expressway

Part of Delhi–Mumbai Expressway in India From Wikipedia, the free encyclopedia

The DND–Faridabad–KMP Expressway, formally known as NH-148NA is a 59 km long, 6-lane wide access-controlled expressway in Delhi NCR, India.[2] It connects the junction of DND Flyway and Ring Road at Maharani Bagh in Delhi with KMP Expressway at Khalilpur, Nuh district (near Sohna) in Haryana. The NH-148NA is a spur (branch) of Delhi–Mumbai Expressway project. This expressway will have an additional 31 km long spur from Sector-65, Faridabad bypass to Jewar Airport.[3]

Length59 km (37 mi)
Existed12 November 2024–present
Major intersectionsSpur to Jewar Airport
Quick facts Route information, Length ...
DND–KMP Expressway
(NH–148NA)[1]
DND KMP Exp.jpg
Route information
Maintained by National Highways Authority of India (NHAI)
Length59 km (37 mi)
Existed12 November 2024–present
Major junctions
North endDND Flyway, Maharani Bagh, Delhi
Major intersectionsSpur to Jewar Airport
South endKMP, Khalilpur, Nuh district, Haryana
Location
CountryIndia
StatesDelhi, Haryana and Uttar Pradesh
Major citiesNew Delhi, Noida, Faridabad, Ballabgarh, Sohna & Jewar
Highway system
Close

The DND/ Maharani Bagh interchange and Kalindi Kunj metro are the 2 entry points in the state of Delhi. In Haryana, it passes entirely through existing Faridabad bypass road. The HSVP has transferred the Faridabad bypass to NHAI for the construction of NH–148NA highway. The construction work was started in May 2021 and 20 km stretch from KMP interchange to NH-2 interchange at Kail Gaon (Ballabhgarh) has been opened on 12 February 2023.

The 26km part from Sector 65 to Sohna in Faridabad has been opened for traffic in 2023.[4] The 24 km long stretch from Jaitpur/ Mithapur in Delhi to Sector-65 in Faridabad has been opened to public on 12 November 2024.[5] The remaining 9 km part from Mithapur to DND was supposed to be ready by May 2025 but is delayed and will open sometime in 2026, probably before June.

History

Overview: Delhi–Mumbai Expressway

The construction work of the Delhi–Mumbai Expressway is divided by the NHAI into 4 sections, with a total of 52 tenders/ construction packages, as given below. The entire 1,350 km long expressway is expected to be completed by January 2025.

More information Section, Length in km ...
Section Length in km No. of packages State-wise packages Status
DNDFaridabadKMP 59 03 1 in Delhi and 2 in Haryana Partially Completed
SohnaKMPVadodara 844 31 3 in Haryana, 13 in Rajasthan, 9 in Madhya Pradesh and 6 in Gujarat Completed Sohna-KMP-Kota and Chechat to Thandla, remaining under-construction as of October 2025.
VadodaraVirar 354 13 10 in Gujarat and 3 in Maharashtra Completed Vadodara-Kharel section, remaining under-construction as of March 2026.
VirarJNPT 92 05 5 in Maharashtra Under-construction as of March 2026.
Close

Main DND-KMP Expressway

For the main DND-KMP Expressway, on 1 March 2019, after foundation stone of NH-148NA was laid by Union Minister Nitin Gadkari in Mithapur in Delhi,[6] NHAI invited bids in December 2019 for construction in 3 packages under Bharatmala Pariyojana,[7] and in July 2020 the work was awarded by to DRA Infracon Private Limited (Package-1 & Package-2)[8] and to DRA Infracon Private Limited (Package-3) in August 2020.[9][10][11] Package-3 was completed in 2023, and reamining two packages were completed in 2024, thus completing the maining route.[12][13]

The construction work of the 'DND–Faridabad–KMP' section was awarded by the National Highways Authority of India (NHAI) to Dineshchandra R. Agrawal Infracon Private Limited (DRA Infracon) in August 2020.[14] This project will reduce congestion on Ashram to Ballabhgarh route (via Badarpur). In Haryana it will have multiple Flyovers and a 3-lane service road on either side of Faridabad bypass road. The NHAI has divided the construction work of 59 km long DND–Faridabad–KMP section of Delhi–Mumbai Expressway project into three packages and awarded it to DRA Infracon. Its construction cost is around 5,332 crores (including land acquisition cost).[15][8]

More information Sr No, Package ...
Sr No Package Length in km Value in crores State Status
1. Junction of DND Flyway & Ring Road in Delhi to Jaitpur–Pushta road in Delhi 09 1,881 Delhi Under Construction[16]
2. Jaitpur–Pushta road in Delhi to Sector-62/65 dividing road in Faridabad 24 1,832 Delhi & Haryana Completed 12 November 2024
3. Sector-62/65 dividing road in Faridabad to KMP Expressway at Khalilpur in Nuh district 26 1,619 Haryana Completed 12 February 2023
Close

Faridabad-Jewar Expressway spur

The NHAI had announced in August 2021, that an additional 31 km long spur will also be constructed from Noida International Airport in Jewar to Faridabad bypass road on this expressway.[17] In July 2022, the tender was awarded Apco Infratech Pvt Ltd.[18][19]

More information Spur Package, Length in km ...
Spur Package Length in km Value in crores State
Faridabad bypass (Sector 65), via interchange with EPE at Mohna, to Yamuna Expressway at Dayanat Pur village, north of Jewar 31 3,630[20](Revised Cost) Haryana and UP
Close

Route

Main DND-KMP Expressway route

The NH–148NA highway connects Sarai Kale Khan & Kalindi Kunj (Delhi), Noida, Jewar, Faridabad and Ballabhgarh to the main alignment of Delhi–Mumbai Expressway via an interchange at Khalilpur, Nuh district (Haryana).[21][22]

Delhi (12 km)

7 km out of 9 km route of in Delhi state is elevated with two-level crossings at 4 locations of the Delhi Metro rail line (near Okhla Vihar and Kalindi Kunj metro station), making it the 1st expressway in India to cross above elevated metro rail line. NH-148NA exits Delhi at MCD Toll Plaza (near Mithapur) which is 12.5 km from the DND starting point.

Haryana (47 km)

Faridabad-Jewar Airport Expressway spur

6-lane (expandable to 8-lanes) 31.4 km expressway with additional 10 km service roads, will cuts down Faridabad-Jewar Airport travel time from 90 minutes to 15 to 30 minutes.[24][25][26]

  • Haryana (Faridabad), 24.1 km:[25]
    • Faridabad Sector-65 bypass, route begins from DND–KMP Expressway.[17]
    • EPE interchange at Mohna village.[17]

Status updates

  • Main DND-KMP Expressway:
    • 2024: Total 50 km completed and operational except Package 1 of 9 km[16]
  • Faridabad-Jewar Airport Expressway spur:
    • 2022 Jul: tender awarded to Apco Infratech Pvt Ltd.[18]
    • 2025 Oct: 53% completed, Jewar Airport to Haryana borer will be completed by December 2025, remaining route from Haryana border to Palwal/Faridabad will be completed by December 2026.[25][26]
    • 2026 Mar: 1200 pillars completed, progress on track for on-time completion in April 2027.[24]