2014 Bangladesh blackout
From Wikipedia, the free encyclopedia
The 2014 Bangladesh blackout was a power outage that occurred across Bangladesh on the morning of November 2, 2014.[1][2] The blackout lasted for almost 10 hours.[3][4]
The blackout began after a technical issue in the transmission line distributing power from India.[5][6][7]
Bangladesh had a severe generation deficit relative to demand, and normal system operations already rationed electricity in rolling blackouts. Following a transmission line failure, Bangladesh could not increase local generation to match demand; all local generation was already in use. Nor could Bangladesh easily import power; it had no synchronous links to the much larger Indian grid. Instead, Bangladesh relied on underfrequency load shedding to temporarily increase the blackout size and stabilize the grid.[2]
Around 11:30 pm on November 1, the (asynchronous) HVDC connection between India and Bangladesh failed, removing 444 MW of imported power. Because the event occurred late at night, the circuits attached to underfrequency relays were less heavily loaded than usual, and could not restore the nominal system 50 Hz frequency, settling at 49 Hz. The persistent disturbance then caused the system to collapse.[2]