Balloki Power Plant
From Wikipedia, the free encyclopedia
| Balloki Power Plant | |
|---|---|
![]() | |
| Official name | Balloki Power Plant |
| Country | Pakistan |
| Location | Balloki, Chunian, Punjab |
| Coordinates | 31°11′19″N 73°53′22″E / 31.1887°N 73.8895°E |
| Status | Operational |
| Construction began | November 2015 |
| Commission date | 2018 |
| Construction cost | $570.87 million[1] |
| Owners | National Power Parks Management Company Pvt. Ltd (EPC: Harbin Electric International Company Limited) |
| Thermal power station | |
| Primary fuel | Liquefied natural gas |
| Combined cycle? | Yes |
| Power generation | |
| Nameplate capacity | 1,223 MW |
| External links | |
| Website | nppmcl.com |
The Balloki Power Plant is a 1,223 MW natural gas power plant completed in mid 2018 in Pattoki, in the Punjab province of Pakistan. Groundbreaking was commenced on November 11, 2015, and construction was scheduled for completion by December 2017.[2] The project utilizes regasified liquefied natural gas (RLNG) for fuel, with diesel as an alternate backup. A 40 kilometer long transmission line with a capacity of 500 kilovolts was also constructed between the new plant and a grid station in southern Lahore.[3]
Bidding was open to international firms for the 82 billion rupee project.[4] China's Harbin Electric Company was announced as the lowest evaluated bidder for the project on October 2, 2015, having offered a levelized electricity cost of 7.973 cents per unit, outbidding the Turkish conglomerate Enka İnşaat ve Sanayi A.Ş. and GE Consortium which both stood in second with 8.185 cents per unit tariff, followed by China Machinery Eng Co (CMEC) & SEFC at 8.304 cents, and Hyundai Engineering at 8.332 cents per unit.[5]
Plans for the project call for private sector investment to construct the plant, with the private company then selling electricity to the government of Pakistan at pre-negotiated rates. It is not financed under CPEC projects. As the project is to be constructed largely by the private sector, financing loans for the project do not fall under the concessionary loan agreement which finances CPEC projects, but it will still qualify for subsidized loans with an interest rate of 5% which are to be dispersed by the Exim Bank of China.[6] For comparison, loans for previous Pakistani infrastructure projects financed by the World Bank carried an interest rate between 5% and 8.5%,[2] while interest rates on market loans approach 12%.[4]
