Changsha Metro

Rapid transit system in Changsha, Hunan, China From Wikipedia, the free encyclopedia

The Changsha Metro (officially 长沙轨道交通; chángshā guǐdào jiāotōng; usually called 长沙地铁; chángshā dìtiě) is a rapid transit system in Changsha and Xiangtan. The first operational line, Line 2, commenced service on April 29, 2014, making Changsha the 18th city in mainland China to open a rapid transit system.[1]

Native name长沙轨道交通
Transit typeRapid transit
Quick facts Overview, Native name ...
Changsha Metro
Platform of Dujiaping station
Platform of Dujiaping station
Overview
Native name长沙轨道交通
OwnerChangsha Government
LocaleChangsha and Xiangtan, Hunan, China
Transit typeRapid transit
Number of lines6
Number of stations140
Daily ridership2,580,169 (2023)
4,675,000 (2025 peak)
Websitehttp://www.hncsmtr.com/
Operation
Began operationApril 29, 2014; 11 years ago (2014-04-29)
Operator(s)Changsha Metro Corporation Ltd.
CharacterElevated, underground
Technical
System length217.78 kilometres (135.32 mi)
System map

Close

Lines in operation

More information Line, Terminals (District) ...
Line Terminals
(District)
Commencement Newest
extension
Length Stations
 1  Jinpenqiu
(Kaifu)
Shangshuangtang
(Yuhua)
2016 2024 33.43 km (20.77 mi) 25
 2  West Meixi Lake
(Yuelu)
Guangda
(Changsha Co.)
2014 2015 26.579 km (16.515 mi) 23
 3  Guangsheng
(Changsha Co.)
Xiangtan North Railway Station
(Yuhu, Xiangtan)
2020 2023 53.69 km (33.36 mi) 33
 4  Guanziling
(Wangcheng)
Dujiaping
(Changsha Co.)
2019 33.50 km (20.82 mi) 25
 5  Maozhutang
(Yuhua)
Shuiduhe
(Changsha Co.)
2020 22.50 km (13.98 mi) 18
 6  Xiejiaqiao
(Wangcheng)
Huanghua Airport T1 & T2
(Changsha Co.)
2022 48.11 km (29.89 mi) 34
Total 217.78 km (135.32 mi) 140
Close
Changsha Railway Station metro entrance
Juzizhou Qinglian station entrance

Line 1

Line 1 construction began in 2010 and was opened on June 28, 2016.[1][2] A 9.9-kilometre (6.2 mi) extension to Line 1 opened in 2024. Line 1 has a line length of 33.43 kilometres (20.77 mi) with 25 stations, of which 3 is elevated and 22 are underground.[3] The construction budget was 14.2 billion RMB.[1] Line 1 is red on system maps.

Line 2

Line 2 is a line running from west to east in Changsha. It was opened on April 29, 2014[4] and extended in December 2015. The line is 26.6 kilometres (16.5 mi) long with 23 stations. Line 2 is light blue on system maps.

Line 3

Line 3 started construction on January 3, 2014. The line opened on June 28, 2020.[5] Line 3 has a total length of 53.69 kilometres (33.36 mi) with 33 stations. The line travels between Xiangtan North railway station and Guangsheng station. A southern extension was opened on June 28, 2023.[6] Line 3 is yellow-green on system maps.[7]

Line 4

Line 4 started construction on December 31, 2014. The line opened on May 26, 2019, with 25 stations.[8] Line 4 has a total length of 33.5 kilometres (20.8 mi) with 25 stations.[9] The line travels between Guanziling station and Dujiaping station. Line 4 is purple on system maps.[7]

Line 5

Line 5 started construction in 2015.[10] The line opened on June 28, 2020.[5] Line 5 has a total length of 22.5 kilometres (14.0 mi) with 18 stations.[10][9] It travels between Maozhutang station and Shuiduhe station. Line 5 is yellow on system maps.[7]

Line 6

Line 6 opened on June 28, 2022. It runs in an east–west direction, connecting the airport with the downtown. The middle section of Line 6 started construction on November 28, 2017.[11] The middle section has a total length of 30.46 kilometres (18.93 mi) with 23 stations. The 5.5 kilometres (3.4 mi) western section, with 4 more stations, and the 12.03 kilometres (7.48 mi) eastern section with 7 more stations, was completed in 2022.[12] It travels between Xiejiaqiao station and Huanghua Airport T1 and T2 station. Line 6 is dark blue on system maps.

Fares and ticket system

Payment methods

QR code

Passengers can pay their Changsha Metro fares by using QR code. The system supports Alipay, WeChat Pay, UnionPay, the Changsha Metro app, and several other apps. These apps requires one to scan a QR code when entering the fare gate at the origin station and again when exiting at the destination station. The fare is then deducted.

Transport card

Passengers can pay their Changsha Metro fares by using China T-union (TU) cards. Passengers swipe their TU card on the fare gate at the origin station and again when exiting at the destination station.

Single-trip ticket

Passengers can buy a single-trip ticket on ticket machines in the metro stations by using cash as well as Alipay, WeChat Pay, or UnionPay.

Incidents

  • On June 24, 2024, two lines were flooded after a particularly heavy rainstorm, of 65mm.[13] Social media posts showed the escalator entrance at one station completely submerged.[14]

Future development

Short-term expansions

More information Line, Terminals ...
Line Terminals
Status Planned Opening Length
km
Stations Reference
 1 
(North Ext. Phase 2)
Dingzizhen Jinpenqiu Planned TBA 4.63 2 [15]
 2 
(West Ext.)
West Railway Station West Meixi Lake Under Construction[16] 28 December 2026 14.5 11
 4 
(North Ext.)
Baimaxiang Guanziling Under Construction[17] 28 June 2028 15.26 9
 5 
(South Ext.)
Maozhutang Datuo East Planned TBA 8.43 7
 5 
(North Ext.)
Shuiduhe Weisan Road Planned TBA 3.65 2
 6 
(East Ext.)
Huanghua Airport T1 & T2 Huanghua Airport T3 Under Construction 2026 3.62 1
 7  Wulipai Yuntang Under Construction[18] 28 June 2027 17 16
 7 
(East Ext.)
East Coash Station Wulipai Planned TBA 5.46 5
 8  Loop Line[19] Planned TBA 55.5 32 [20]