Cordova Desalination Plant

From Wikipedia, the free encyclopedia

Coordinates10°14′35.4″N 123°56′33.2″E / 10.243167°N 123.942556°E / 10.243167; 123.942556
Estimated output20 million L (5.3 million US gal) per day
Extended output50 million L (13 million US gal) per day
Cordova Desalination Plant
Cordova Desalination Plant is located in Metro Cebu
Cordova Desalination Plant
Location of the CDP within Metro Cebu.
Desalination plant
LocationCordova, Cebu, Philippines
Coordinates10°14′35.4″N 123°56′33.2″E / 10.243167°N 123.942556°E / 10.243167; 123.942556
Estimated output20 million L (5.3 million US gal) per day
Extended output50 million L (13 million US gal) per day
TechnologyReverse osmosis
Operation dateJune 7, 2024 (2024-6-7)

The Cordova Desalination Plant (CDP) is a desalination facility in Cordova in Cebu province, Philippines. It is the first desalination plant in the Philippines.

Isla Mactan Cordova Corporation (IMCC) would be awarded a contract to supply water for the Metropolitan Cebu Water District in June 2021.[1] To fulfill the contract, the construction of a desalination plant in Cordova, Cebu began. Watermatic Philippines, a joint venture of Vivant and Israeli firm WaterMatic International, led the construction.[2]

It is built under a build–operate–transfer scheme under the private-public partnership setup.[3]

On September 7, 2023, the desalination equipment was installed.[4] By that month the whole facility is already 70 percent complete.[5]

The IMCC plant started operations on June 7, 2024, initially producing 5 million L (1.3 million US gal) of processed water daily.,[2] becoming the first desalination plant in the Philippines, where drinking water has only been sourced groundwater and surface water.[6]