| Coordinates | 43°36′50.1″N 104°29′00.7″E / 43.613917°N 104.483528°E |
| Groundbreaking | 4 January 2018 |
| Opened | June 2020 |
| Cost | US$21.17 million |
| Technical details | |
| Grounds | 1.8 hectares |
| Design and construction | |
| Main contractor | N A.B, S&A Trade, San and Baiguulamj |
The Dalanzadgad New Wastewater Treatment Plant (Mongolian: Даланзадгад хотын шинэ цэвэрлэх байгууламж) is a wastewater treatment plant in Dalanzadgad, Ömnögovi Province, Mongolia.
Due to the overcapacity of the existing old treatment plant, a new treatment plant should be constructed. The groundbreaking ceremony for the construction of the new plant was held on 4 January 2018 at the Ministry of Construction and Urban Development. The construction was completed in 2019 by N A.B, S&A Trade, San and Baiguulamj companies. Test run of the plant was carried out in the first half of 2020. In June 2020 the plant went into full operation.[1]
Architecture
The plant stands at a total ground area of 1.8 hectares.[2]