Daqing Saertu Airport (IATA: DQA, ICAO: ZYDQ) is an airport (class 4C) serving the city of Daqing in Heilongjiang Province, China. Construction started in 2007 with a total investment of 500 million yuan, and the airport was opened on 1 September 2009.[2]
Daqing Sartu Airport 大庆萨尔图机场 | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Summary | |||||||||||
| Airport type | Public | ||||||||||
| Serves | Daqing, Heilongjiang, China | ||||||||||
| Location | Sartu District, Daqing, Heilongjiang | ||||||||||
| Opened | 1 September 2009 | ||||||||||
| Coordinates | 46°44′47″N 125°07′56″E | ||||||||||
| Map | |||||||||||
| Runways | |||||||||||
| |||||||||||
| Statistics (2025 [1]) | |||||||||||
| |||||||||||
| Daqing Sartu Airport | |||||||
|---|---|---|---|---|---|---|---|
| Simplified Chinese | 大庆萨尔图机场 | ||||||
| Traditional Chinese | 大慶薩爾圖機場 | ||||||
| |||||||
History
On May 21, 2006, the State Council and the Central Military Commission of China officially approved the construction of Daqing Sartu Airport.[3][4][5]
The construction of Sartu Airport began in October 2008. On August 3, 2009, all functional projects of the airport were completed.[4] The total investment was 434.44 million yuan.[6] On August 13, the airport completed its first test flight, and it officially opened to traffic on September 1.[4] It had a 4C flight zone rating, a 2,600-meter-long runway.[6]
In 2011, the first expansion and renovation project of Daqing Sartu Airport was completed. The project included adding two Class II remote aircraft stands, one dedicated de-icing apron, and one city terminal building.[7] However, the bidding process for the expansion and renovation project was found to have involved illegal and irregular activities. The contract price was more than double the winning bid of 126 million yuan, raising questions about the nature of the bidding process and investment oversight.[8]
In 2019, the "Daqing Sartu Airport Function Enhancement Project" commenced construction, which includes an 8,216.52 square meter international terminal, a connecting boarding bridge, and an immigration control building.[7]
Facilities
The airport has one runway that is 2,600 meters long and 45 meters wide, and a 14,000-square-meter terminal building. It is designed to handle 1.47 million passengers annually by 2020.[2]