Den Chai–Chiang Khong Line

Rail line From Wikipedia, the free encyclopedia

The Den Chai–Chiang Rai–Chiang Khong railway line is a project of the State Railway of Thailand (SRT) and one of two extensions of the Northern Railway Line. Its objective is to support travel and freight in the northern region, including supporting the Chiang Khong freight transfer center currently under construction. This project will connect the North–South Economic Corridor from Thailand to Laos, China, Vietnam, and other economic zones under government policy. Construction was originally scheduled for 2017, but was postponed to 2021. In July 2018, the Cabinet approved the Den Chai–Chiang Rai–Chiang Khong double-track railway project, covering a distance of 323 km, with a total budget of 85.345 billion baht and a project duration of seven years.  The Ministry of Transport urged the SRT to begin land acquisition and bidding by 2021, with a five-year construction period and opening service in 2028.

StatusUnder construction
Termini
Quick facts Overview, Status ...
Den Chai–Chiang Khong Line
Construction of a tunnel in Ngao in December 2024
Overview
StatusUnder construction
OwnerState Railway of Thailand
Termini
Service
TypeInter-city rail
SystemNorthern Line
Operator(s)State Railway of Thailand
History
Opened2028
Technical
Line length323.1 km (200.8 mi)
Number of tracks1
Track gauge1,000 mm (3 ft 3+38 in) metre gauge
Operating speed160 km/h (99 mph)
Close

History

The construction project for the double-track railway line Chum Thong Den Chai - Chiang Rai - Chiang Khong, a distance of 326 kilometers, was previously studied by the Thai government in 1960 and surveyed the area in 1969, designating the route Den Chai - Phrae - Song - Chiang Muan - Dok Kham Tai - Phayao - Pa Daet - Chiang Rai, a total distance of 273 kilometers.

Later, in 1994–1995, the State Railway of Thailand (SRT) hired consultants to review the study results. The conclusion was that the Den Chai Junction – Phrae – Song – Ngao (Lampang) – Phayao – Chiang Rai route would shorten the distance to approximately 246 kilometers. Consequently, in 1996–1998, the SRT spent approximately 2.2 million baht on the project. The SRT then hired a private company to survey, design, and study the impacts, leading to a Royal Decree on land expropriation in 2001. In 2004, the then-government ordered another feasibility study, citing the need to connect with southern China. In 2008, a study was also conducted to connect the border of Chiang Rai Province and China's rail system.

Until 2010–2011, studies began on double-track railways to increase the width to 1.435 meters. In the case of the route in Chiang Rai Province, the route was separated to the second Chiang Saen Mekong River Port in Ban Saeo Subdistrict, Chiang Saen District, and the Thai-Lao Mekong River Bridge in Chiang Khong District.

The latest route studied has a total distance of approximately 323.1 kilometers, with a total of 26 stations passing through Phrae, Lampang, Phayao, and Chiang Rai provinces, and a tunnel will be drilled into the mountain to connect the route to Chiang Khong District.

In 2018, the Cabinet approved the construction project of the Den Chai-Chiang Rai-Chiang Khong double-track railway line, consisting of 26 stations, 4 cargo handling yards, 1 container storage yard, 4 railway tunnels, 40 roads over the railway, and 102 roads under the railway. The project began in Phrae, Lampang, Phayao, Chiang Rai, and Chiang Khong provinces.

On March 19, 2021, the State Railway of Thailand began opening bid envelopes via the electronic procurement system (e-bidding) from March 19 to May 17, 2021, and submitted proposals on May 18, 2021. The construction is divided into three contracts: Contract 1, Den Chai- Ngao section, 103 km long; Contract 2, Ngao-Chiang Rai section, 132 km long; and Contract 3, Chiang Rai-Chiang Khong section, 87 km long. The construction schedule is 5 years, with service opening in 2028.

On June 27, 2021, the Royal Gazette website published the land expropriation demarcations in some areas of Den Chai, Sung Men, Mueang Phrae, Nong Muang Khai, and Song Districts in Phrae Province ; Ngao District in Lampang Province ; Mueang Phayao, Dok Khamtai, and Phu Kam Yao Districts in Phayao Province; and Pa Daet, Thoeng, Mueang Chiang Rai, Wiang Chai, Wiang Chiang Rung, Doi Luang, and Chiang Khong Districts in Chiang Rai Province   to construct the Den Chai–Chiang Rai–Chiang Khong Railway Project 2021. This Royal Decree will take effect the day after its publication in the Royal Gazette (May 28, 2021). The land expropriation covers over 10,000 rai and 7,000 plots of land.[1]

On December 16, 2021, Mr. Nirut Maneephan, Governor of the State Railway of Thailand, approved the construction contract for the Den Chai–Chiang Rai–Chiang Khong double-track railway project, valued at 72.92 billion baht, from three contractors: Contract 1, the Den Chai–Ngao section, is being awarded by Italian-Thai Development Public Company Limited (ITD) in collaboration with Nawarat Patanakarn Public Company Limited; Contract 2, the Ngao–Chiang Rai section, is being awarded by the CKST Joint Venture, comprising CH. Karnchang Public Company Limited, Sino-Thai Engineering and Construction Public Company Limited, and Buriram Panasit Co., Ltd.; and Contract 3, the Chiang Rai–Chiang Khong section, is being awarded by the CKST Joint Venture, comprising CH. Karnchang Public Company Limited, Sino-Thai Engineering and Construction Public Company Limited, and Chiang Mai Construction Co., Ltd.[2]

On December 29, 2021, at the State Railway of Thailand, Mr. Nirut Maneephan, Governor of the State Railway of Thailand, signed a contract for the construction of the Den Chai-Chiang Rai-Chiang Khong double-track railway project, as well as signing an Integrity Pact for cooperation in preventing corruption in government procurement between the State Railway of Thailand, which is the owner of the project [3]

When the project is completed, it will support travel, border trade, tourism, and logistics in the upper northern region, including supporting the Chiang Khong goods transfer center, connecting trade along the North-South Economic Corridor from Thailand to Laos, Burma, and southern China. It will also help accelerate the development of the Chiang Rai Special Economic Zone, which the government is pushing for.[4]

Districts through which the route passes

More information District, province ...
District province
Chiang Saen / Doi Luang / Wiang Chiang Rung / Chiang Khong / Wiang Chai / Chiang Rai / Pa Daet / Thoeng Chiang Rai
Phu Kamyao / Phayao / Dok Kham Tai Phayao
Ngao Lampang
Song / Nong Muang Khai / Phrae / Sung Men / Den Chai spread
Close

Construction contract

More information Contract, Period ...
Contract Period Distance

(kilometers)

Auction winner Progress 20.661%

(as of September 2024)

Progress 50.496%

(as of December 2025)

1 Den Chai-Ngao 104 ITD-Nawarat Joint Venture 10.44% 47.618%
2 Ngao-Chiang Rai 132 CKST-DC 2 Joint Venture 24.35% 56.726%
3 Chiang Rai-Chiang Khong 87 CKST-DC 3 Joint Venture 29.55% 45.798%
Close

Construction progress

More information Date, Progress ...
Date[5] Progress Advancement by
November 2022 0.52%
December 2022 0.606% 0.094%
January 2023 0.743% 0.137%
February 2023 0.825% 0.082%
March 2023 0.925% 0.1%
April 2023 1.021% 0.096%
May 2023 1.21% 0.189%
June 2023 1.485% 0.275%
July 2023 1.789% 0.304%
August 2023 2.02% 0.231%
September 2023 2.423% 0.403%
October 2023 3.016% 0.593%
November 2023 3.773% 0.757%
December 2023 4.832% 1.059%
January 2024 5.449% 0.617%
February 2024 6.695% 1.246%
March 2024 8.054% 1.359%
April 2024 9.409% 1.355%
May 2024 11.288% 1.879%
June 2024 12.675% 1.387%
July 2024 15.264% 2.589%
August 2024 16.852% 1.588%
September 2024 18.355% 1.503%
October 2024 19.88% 1.525%
November 2024 21.579% 1.699%
December 2024 23.99% 2.411%
January 2025 25.785% 1.795%
February 2025 28.182% 2.397%
March 2025 31.974% 3.792%
April 2025 33.72% 1.746%
May 2025 36.067% 2.347%
June 2025 38.341% 2.274%
July 2025 40.295% 1.954%
August 2025 41.986% 1.691%
September 2025 43.984% 1.998%
October 2025 46.112% 2.128%
November 2025 48.62% 2.508%
December 2025 50.496% 1.876%
Close