Fangchenggang Nuclear Power Plant

Nuclear power plant in Guangxi, China From Wikipedia, the free encyclopedia

Fangchenggang Nuclear Power Plant (simplified Chinese: 防城港核电站; traditional Chinese: 防城港核電站; pinyin: Fángchénggǎng hédiànzhàn), also known as Fangchenggang Hongsha Nuclear Power Plant (simplified Chinese: 防城港红沙核电站; traditional Chinese: 防城港紅沙核電站), is a nuclear power plant in Fangchenggang, near Hongsha Village(simplified Chinese: 红沙村; traditional Chinese: 紅沙村),[1] autonomous region of Guangxi (Guangxi Zhuang Autonomous Region) in the People's Republic of China. A total of six reactors are planned to operate at the Fangchenggang site. Units 1 and 2 are both CPR-1000s, units 3–4 are Hualong Ones, units 5–6 are planned also to be Hualong One reactors. Fangchenggang 3 and 4 will be the reference plant for the proposed Bradwell B plant in the UK.[2]

CountryPeople's Republic of China
LocationHongsha, Gangkou, Fangchenggang, Guangxi
Coordinates21°40′15″N 108°33′30″E
StatusOperational
Quick facts Country, Location ...
Fangchenggang Nuclear Power Plant
CountryPeople's Republic of China
LocationHongsha, Gangkou, Fangchenggang, Guangxi
Coordinates21°40′15″N 108°33′30″E
StatusOperational
Construction began30 July 2010
Commission date1 January 2016
OperatorGuangxi Fangchenggang Nuclear Power Group
Nuclear power station
Reactor typeCPR-1000, HPR-1000
Cooling sourceGulf of Tonkin
Power generation
Units operational4 × 1,000 MW
Units planned2 × 1000 MW
Nameplate capacity4,000 MW
Close

The plant is located about 54 kilometres from the border with Vietnam. It is a project of Guangxi Fangchenggang Nuclear Power Group, a joint venture between China Guangdong Nuclear Power Co (CGNPC) and Guangxi Investment Group.[3]

Unit 1 was connected to the electricity grid on 25 October 2015.[4] Unit 1 is commercially operating starting on 1 January 2016. [5]

Construction works for Unit 3 started in December 2015.[6] Unit 3 first concrete pour occurred on 24 December 2015.[7] First concrete for Unit 4 followed one year later, on 23 December 2016.[8]

Reactor data

The Fangchenggang Nuclear Power Plant consist of 4 operational reactors and 2 reactors planned.

More information Unit, Type /Model ...
UnitType /ModelNet
power
Gross
power
Thermal
power
Construction
start
First
criticality
Grid
connection
Operation
start
Notes
Phase I
Fangchenggang 1PWR / CPR-1000 1000 MW1086 MW2905 MW 2010-07-302015-10-132015-10-252016-01-01 [9]
Fangchenggang 2PWR / CPR-1000 1000 MW1086 MW2905 MW 2010-12-232016-06-292016-07-152016-10-01 [10]
Phase II
Fangchenggang 3PWR / HPR1000 1000 MW1180 MW3150 MW 2015-12-242022-12-272023-01-102023-03-25 [11][12]
Fangchenggang 4PWR / HPR1000 1000 MW1180 MW3150 MW 2016-12-232024-04-032024-04-092024-05-25 [13]
Fangchenggang 5PWR / HPR1000 1000 MW1180 MW3150 MW [14][15]
Fangchenggang 6PWR / HPR1000 1000 MW1180 MW3150 MW [14][15]