Gipsy Patch Lane closed in March 2020 to allow the bridge to be replaced.[2] The bridge was originally planned to be installed over Easter but work was delayed by the COVID-19 pandemic.[3] Following news of the delay, a route for pedestrians and cyclists under the bridge was restored in April 2020.[4]
The new 4,260-tonne bridge was constructed on site near the original bridge.[5] The original bridge was demolished on 27 October 2020. The operation to move the new bridge into place began the following day. However, the transporters carrying it became stuck in mud 30 metres (98 ft) short of the desired location.[6][7] The bridge was eventually moved into position on 14 November and the railway was reopened on 23 November, 16 days later than planned.[3]
In November 2021, Gipsy Patch Lane reopened to westbound traffic.[2] The road reopened to traffic in both directions on 24 April 2022.[3][8]