IRS-class barge

Service barge From Wikipedia, the free encyclopedia

The IRS-class ACTCM barge is a series of 19 ammunition barge built for the Indian Navy by two MSME shipyards. Under the project, 11 Ammunition Cum Torpedo Cum Missile (ACTCM) barges are being built by Suryadipta Projects Pvt Ltd of Thane, Maharashtra while 8 Missile Cum Ammunition (MCA) barges are being built by SECON Engineering Projects Pvt Ltd of Visakhapatnam, Andhra Pradesh. The contracts with the shipyards were signed on 5 March 2021 and 19 February 2021, respectively.[2][3][4] The barges are either based at INS Tunir, Naval Missile Depot at Mumbai, or Naval Ammunition Depot (NAD), Karanja at Naval Dockyard (Mumbai).

Builders
  • Suryadipta Projects Pvt Ltd.
  • SECON Engineering Projects Pvt. Ltd.
Operators Indian Navy
Planned19
Completed19
Quick facts Class overview, Builders ...
Class overview
Builders
  • Suryadipta Projects Pvt Ltd.
  • SECON Engineering Projects Pvt. Ltd.
Operators Indian Navy
Planned19
Completed19
Active19
General characteristics
Length16.5 m (54 ft 2 in)
Beam6 m (19 ft 8 in)
Height3.1 m (10 ft 2 in)
Draught2 m (6 ft 7 in)
Capacity100 tonnes (98 long tons) full load[1]
Crew7 (1 officer, 6 civilian)
Close

The model testing of the barge during design stage was undertaken at NSTL, Visakhapatnam, Andhra Pradesh under relevant Naval Rules and Regulation of Indian Register of Shipping.[5][6] The barges are being built under Atmanirbhar Bharat and Make in India initiative of the government of India.[2][6][7] The final barge was delivered by Suryadipta Projects was delivered on 9 September 2025 and inducted in to Indian Navy on 17 October 2025. Under a separate contract Suryadipta Projects is also building 4 sullage barge for the Indian Navy.[8]

Description

IRS-class Ammunition-Cum-Torpedo-Cum-Missile (ACTCM) barge are to be inducted in the Indian Navy to undertake the mission needs for transport, embarking or disembarking of ammunition, torpedo, missile, articles, etc. on the navy ships, thereby providing impetus to operational commitments of the navy both alongside jetties and outer harbors boosting operational readiness and effectiveness. The ACTCM barges are also referred to MCA (Missile Cum Ammunition) barges, but all are designated as Large Scale Additive Manufacturing (LSAM).[7] All major and auxiliary equipment/systems on the barge, which is set to have a service life of 30 years have been sourced from indigenous manufacturers.[9]

Delivery of the first barge LSAM 15 (Yard 125) by Suryadipta Projects to Indian Navy was done on 9 June 2023.[10] LSAM 7 to 14 has been built by SECON Engineering and LSAM 15 to 25 has been built by Suryadipta Projects.[11][12] The barge has a cargo hold of 100 tonnes. The barge has ample facilities for fire fighting, power generation, and crew accommodation.[13][14][3]

By October 2025, the entire consignment of eight MCA barges and eleven ACTCM barges have been delivered and inducted in to service.[15][16] The last of the barges by Suryadipta Projects was launched on 9 September 2025 after a gap of 6 months.[17] The final barge was delivered by Suryadipta Projects and inducted in to Indian Navy on 17 October 2025.[8]

List of units

More information Pennant Number, Builder ...
Pennant Number Builder Yard No. Launched Delivered Base
LSAM 7 SECON Engineering Projects

(under MCA barge project)

75 24 February 2023[18] 18 July 2023[19] INS Tunir,[a] Mumbai
LSAM 8 76 18 August 2023[20] 19 October 2023[21] NAD[b] Karanja, Mumbai
LSAM 9 77 23 September 2023[22] 22 November 2023[23] INS Tunir,[c] Mumbai
LSAM 10 78 20 November 2023[24] 28 December 2023[25] NAD[d] Karanja, Mumbai
LSAM 11 79 14 February 2025[26] March 7, 2025[27][28] INS Tunir,[e] Mumbai
LSAM 12 80 10 October 2024[29] 22 November 2024 [30] NAD[f] Karanja, Mumbai
LSAM 13 81 10 June 2024[31] 26 September 2024[32] INS Tunir,[g] Mumbai
LSAM 14 82 12 December 2024[33] 7 January 2025[15] NAD[h] Karanja, Mumbai
LSAM 15 Suryadipta Projects

(under ACTCM barge project)

125 10 February 2023[34] 9 June 2023[35]
LSAM 16 126 20 July 2023[36] 7 September 2023[37]
LSAM 17 127 27 October 2023[38] 30 November 2023[39] NAD[i] Karanja, Mumbai
LSAM 18 128 28 February 2024[2] 29 March 2024[40]
LSAM 19 129 24 January 2024[41] 5 March 2024[42]
LSAM 20 130 29 April 2024[43] 29 May 2024[44]
LSAM 21 131 5 September 2024[45] 4 October 2024[46]
LSAM 22 132 30 November 2024[47] 6 January 2025[48]
LSAM 23 133 1 February 2025[49] 12 March 2025[50]
LSAM 24 134 26 March 2025[51] 22 April 2025[52]
LSAM 25 135 9 September 2025[17] 17 October 2025[16] Naval Dockyard (Mumbai)
Close

Notes

  1. Naval missile depot
  2. Naval Armament Depot
  3. Naval missile depot
  4. Naval Armament Depot
  5. Naval missile depot
  6. Naval Armament Depot
  7. Naval missile depot
  8. Naval Armament Depot
  9. Naval Armament Depot

See also

References

Related Articles

Wikiwand AI