Moyo General Hospital

From Wikipedia, the free encyclopedia

Coordinates03°38′59″N 31°43′38″E / 3.64972°N 31.72722°E / 3.64972; 31.72722
Moyo General Hospital
Uganda Ministry of Health
Moyo General Hospital is located in Uganda
Moyo General Hospital
Geography
LocationMoyo, Moyo District, Northern Region, Uganda
Coordinates03°38′59″N 31°43′38″E / 3.64972°N 31.72722°E / 3.64972; 31.72722
Organisation
Care systemPublic
TypeGeneral
Services
Emergency departmentI
Beds176
History
Founded1972
Links
Other linksHospitals in Uganda

Moyo General Hospital also Moyo Hospital, is a hospital in the Northern Region of Uganda.

The hospital is located in the central business district of Moyo Town, in Moyo District, in West Nile sub-region, in Northern Uganda, approximately 160 kilometres (99 mi) northeast of Arua Regional Referral Hospital.[1]

This is approximately 157 kilometres (98 mi) northwest of Gulu Regional Referral Hospital.[2] The coordinates of Moyo General Hospital are:03°38'59.0"N, 31°43'38.0"E (Latitude:3°38'59.0"N; Longitude:31°43'38.0"E).[3]

Overview

The hospital was built during the late 1960s and was commissioned by Idi Amin in 1972. The hospital infrastructure is dilapidated and the equipment is antiquated or non-functional. The hospital is severely under-staffed, employing only 60 nurses out of the 120 needed. As of January 2016, the facility had no functioning ambulance.[4]

Renovations

In 2013, the government of Uganda secured funding from the World Bank, to repair and renovate certain hospitals, Moyo General Hospital among them.[5] The US$4,541,931.32 contract was awarded to Prism Construction Company Limited.[6] Work that started in February 2014[7] consists of the following, among others:[8]

  • Build new emergency department (casualty department)
  • Build a new, larger outpatient department
  • Build a new building to house the diesel-powered electricity generator
  • Build a new placenta disposal pit
  • Build a new medical waste disposal pit
  • Build a laundry facility for patients' families
  • Build a kitchen and dining room for patients' families
  • Build ventilated improved pit latrines for patient families and outpatients
  • Construct two new staff houses

The construction started in February 2014 with expected completion in October 2015.[7] However, due to multiple delays,[9][10] the new expected completion date is June 2016.[7]