New Central Wastewater Treatment Plant
From Wikipedia, the free encyclopedia
| New Central Wastewater Treatment Plant | |
|---|---|
Төв цэвэрлэх байгууламж | |
![]() Interactive map of the New Central Wastewater Treatment Plant area | |
| General information | |
| Type | wastewater treatment plant |
| Location | Songino Khairkhan, Ulaanbaatar, Mongolia |
| Coordinates | 47°54′09″N 106°45′45″E / 47.90250°N 106.76250°E |
| Groundbreaking | 28 February 2019 |
| Cost | US$262.7 million |
| Technical details | |
| Grounds | 17.7 hectares |
The New Central Wastewater Treatment Plant (Mongolian: Төв цэвэрлэх байгууламж) is a wastewater treatment plant under construction in Songino Khairkhan District, Ulaanbaatar, Mongolia.
The feasibility study to establish the plant was done in 2015. The construction of the plant was officiated on 2 February 2019 and constructed officially started on 28 February 2019 in a groundbreaking ceremony officiated by Prime Minister Ukhnaagiin Khürelsükh.[1] On 31 March 2022, concrete started to be poured into the inner walls of the plant three reaction tanks.[2] In July 2025, the plant received its first trial inflow of.[3]
Architecture
The plant is constructed in a 17.7 hectares of land. There are 35 buildings being constructed at the plant site.[1]
Technical specifications
Once completed, the plant will have a processing capacity of 250,000 m3 of wastewater per day.[2]