Niederaichbach Nuclear Power Plant

From Wikipedia, the free encyclopedia

Official nameKernkraftwerk Niederaichbach
CountryGermany
Coordinates48°36′17″N 12°18′14″E / 48.60472°N 12.30389°E / 48.60472; 12.30389
Niederaichbach Nuclear Power Station
Reactor building (far right) during decommissioning
Official nameKernkraftwerk Niederaichbach
CountryGermany
LocationNiederaichbach
Coordinates48°36′17″N 12°18′14″E / 48.60472°N 12.30389°E / 48.60472; 12.30389
StatusDecommissioned
Construction beganJune 1, 1966
Commission dateJanuary 1, 1973
Decommission dateJuly 21, 1974
Construction cost230,000,000 DM
OwnerKarlsruhe Institute of Technology
OperatorKernkraftwerk Niederaichbach GMBH
Nuclear power station
Reactors1 x 106 MWe
Reactor typeHeavy Water Gas Cooled Reactor
Thermal capacity321 MWt
Power generation
Capacity factor1.1%

Niederaichbach Nuclear Power Plant (German: Kernkraftwerk Niederaichbach (KKN)) was a German nuclear plant in Niederaichbach, Bavaria. The plant consisted of one heavy water gas cooled (HWGC) reactor with a gross capacity of 106 MWe. Safety and maintenance issues caused the reactor to be decommissioned after only a year and a half in operation. It was the first nuclear plant in Europe to be completely decommissioned, with the final work being completed in autumn 1995.[1]

Although located at the same location as the Isar Nuclear Power Plant, the Niederaichbach plant used a different reactor type and was decommissioned five years before construction of the Isar plant was completed.

In the late 1950s the government of Bavaria became interested in developing nuclear power within the state. Construction began in 1966. Only a year later, Hans Matthöfer, German Minister of Education and Technology, remarked that the project had "No technological future", due to the limitations of its experimental HWGC reactor.[2] Nevertheless, construction continued, with others in the Bavarian government hopeful that its construction and operation would provide much needed technological and operational experience.

Construction was completed in 1972 at the cost of 230 million Deutsche Marks. It began operation in 1973, but struggled to produce anywhere close to its capacity. After problems with the steam turbines in mid-1974 the reactor was taken offline and decommissioned.[3] In its year and a half of operation it generated only 20,000 MWh of energy, equivalent to just 18 days of full capacity operation or a capacity factor of just 1.1%.[2][4]

Decommissioning