Rio Madeira HVDC system
From Wikipedia, the free encyclopedia
21°49′59″S 48°20′52″W / 21.83306°S 48.34778°W ( Araraquara)
21°37′10″S 48°35′24″W / 21.61944°S 48.59000°W ( Araraquara)
| Rio Madeira HVDC system | |
|---|---|
![]() Location of Rio Madeira HVDC system | |
| Location | |
| Country | Brazil |
| State | Rondônia, São Paulo |
| Coordinates | 08°54′53″S 63°57′27″W / 8.91472°S 63.95750°W ( Porto Velho) 21°49′59″S 48°20′52″W / 21.83306°S 48.34778°W ( Araraquara) 21°37′10″S 48°35′24″W / 21.61944°S 48.59000°W ( Araraquara) |
| From | Porto Velho, Rondônia |
| To | Araraquara, São Paulo |
| Construction information | |
| Manufacturer of substations | ABB, Alstom Grid |
| Commissioned | 2013-2014 |
| Technical information | |
| Type | Transmission |
| Type of current | HVDC |
| Total length | 2,375 km (1,476 mi) |
| Power rating | 2 x 3150 MW |
| DC voltage | ±600 kV |
| No. of poles | 4 |
The Rio Madeira HVDC system is a high-voltage direct current transmission system in Brazil, built to export power from new hydro power plants on the Madeira River in the Amazon Basin to the major load centres of southeastern Brazil. The system consists of two converter stations at Porto Velho in the state of Rondônia and Araraquara in São Paulo state, interconnected by two bipolar ±600 kV DC transmission lines with a capacity of 3,150 megawatts (4,220,000 hp) each. In addition to the converters for the two bipoles, the Porto Velho converter station also includes two 400 MW back-to-back converters to supply power to the local 230 kV AC system. Hence the total export capacity of the Porto Velho station is 7100 MW: 6300 MW from the two bipoles and 800 MW from the two back-to-back converters. When Bipole 1 commenced commercial operation in 2014, Rio Madeira became the world’s longest HVDC line, surpassing the Xiangjiaba–Shanghai system in China. According to the energy research organisation Empresa de Pesquisa Energética (EPE),[1] the length of the line is 2,375 kilometres (1,476 mi).
The northern (Porto Velho) converter station is connected, via a 500 kV AC collector grid (Coletora Porto Velho), to the new Rio Madeira hydro plant complex. As of January 2013 this consisted of two generating stations: Santo Antônio, close to Porto Velho, with a capacity of 3150 MW, and Jirau, with a capacity of 3750 MW, approximately 100 kilometres (62 mi) away. Both generating plants are of the low-head, so-called run of river type in order to minimise the environmental impact of the project. They use bulb turbines, which are a type of horizontal-axis Kaplan turbine. These have very low inertia compared to other types of hydro-electric generator, and this led to concerns that the turbines could be damaged by over-speed in the event of a sudden interruption to power transmission on the HVDC lines.
Planning of the transmission system
With such a long transmission distance (2375 km), HVDC would seem to be the natural solution for transporting the generated power to the load centres of south-east Brazil, but a very comprehensive techno-economic analysis was nevertheless performed to evaluate the relative benefits of various different solutions. A total of 16 options were initially examined, including three all-DC options at 500 kV, 600 kV and 800 kV, as well as several all-AC options and hybrid DC+AC options. In the end it was concluded that DC, at a transmission voltage of 600 kV (the same as for the Itaipu scheme in southern Brazil) was the preferred option.[2]
Nevertheless, two of the other options (an all-AC option and a hybrid AC+DC option) were also taken forward to the second stage of project planning. Thus there were three options put forward for the final selection:[1]
- All-DC option: Two ±600 kV, 3150 MW transmission bipoles, plus two 400 MW back to back converters
- Hybrid AC+DC option: One ±600 kV, 3150 MW transmission bipole plus two 500 kV AC lines
- All-AC option: Three 765 kV AC lines
The winner from the three short-listed options was decided by an auction in November 2008 and proved to be the ±600 kV all-DC option. This option was divided into seven separate packages, referred to as Lots 1–7:[1]
- Lot 1: Porto Velho 500 kV AC substation plus two 400 MW back-to-back converters
- Lot 2: Two ±600 kV, 3150 MW converter stations for Bipole 1
- Lot 3: Two ±600 kV, 3150 MW converter stations for Bipole 2
- Lot 4: Two ±600 kV, 3150 MW transmission lines for Bipole 1
- Lot 5: Two ±600 kV, 3150 MW transmission lines for Bipole 2
- Lot 6: Receiving end AC substation
- Lot 7: Grid reinforcement on 230 kV northern system

