The Savannah Tarka Wind Power Station (French: Parc Eolien de la Tarka), also Tarka Wind Power Station, is a planned 250 megawatts wind power energy project, in Niger. The power station is owned and under development by Savannah Parc Eolien de la Tarka (SPET), a subsidiary of independent power producer (IPP), Savannah Energy, with headquarters in the United Kingdom.[1] The wind farm is the first large-scale, grid-ready wind power station in the country and one of the largest in sub-Saharan Africa. Under a long-term power purchase agreement (PPA), the energy generated here will be sold to Société nigérienne d’électricité (NIGELEC), for integration into the Nigerien grid and possibly for sale to the country's neighbors.[2][3]
| Savannah Tarka Wind Power Station | |
|---|---|
![]() | |
| Country | |
| Location | Tarka, Tahoua Department, Tahoua Region, Niger |
| Coordinates | 14°54′13″N 05°12′06″E |
| Status | Proposed |
| Commission date | 2025 Expected |
| Owner | Savannah Energy |
| Power generation | |
| Nameplate capacity | 250MW |
Location
The wind farm would be located in the community of Tarka, near the city of Tahoua, the capital of Tahoua Department and Tahoua Region, in southwestern Niger.[1][2] Tahoua is located approximately 563 kilometres (350 mi) northeast of Niamey, the capital city of Niger.[4]
Overview
The planned generation capacity of this wind farm is 250 megawatts. The design calls for 60 wind turbines. A feasibility study that is planned before 2023, is expected to inform the exact layout of the farm and may adjust the capacity and number turbines. In March 2022, Savannah Energy received authorization from the government of Niger to proceed with the feasibility study. NIGELEC, the national electricity utility parastatal company will buy the energy generated at this power station, under a long-term PPA.[1][2]
Developers
Funding
Savannah Energy plans to fund this renewable energy infrastructure project from internal sources and "project-specific" loans.[3]
Timeline
Other considerations
Savannah Tarka Wind Power Station is expected to add 600 GWh of clean electricity annually to the electric grid of Niger. This will save the country over 400,000 tonnes of carbon dioxide emissions every year. This projects is expected to create 500 jobs during the construction phase.[1][2]