Sturgis Dam

From Wikipedia, the free encyclopedia

Official nameSturgis Dam
CountryUnited States
LocationLockport Township, St. Joseph County, Michigan
Near Centreville, Michigan
Coordinates41°58′12″N 85°32′19″W / 41.969905°N 85.538569°W / 41.969905; -85.538569
Sturgis Dam
Official nameSturgis Dam
CountryUnited States
LocationLockport Township, St. Joseph County, Michigan
Near Centreville, Michigan
Coordinates41°58′12″N 85°32′19″W / 41.969905°N 85.538569°W / 41.969905; -85.538569
PurposePower
StatusOperational
Construction began1909
Opening date1911
Construction cost$190,000
Owner(s)Sturgis, Michigan
Dam and spillways
Type of damEmbankment, earth-fill
ImpoundsSt. Joseph River
Height24 ft (7 m)
Length308 ft (94 m)
Width (crest)22 ft (7 m)
Width (base)800 ft (244 m)
Reservoir
CreatesSturgis Reservoir
Power Station
Operator(s)City of Sturgis
Commission date1909
Turbines2 x 550kw Allis-Chalmers Vertical Shaft Units, 2 x 750kw Allis-Chalmers Horizontal Tube Units

Sturgis Dam is a dam with a hydroelectric power station on the St. Joseph River in Michigan.

The Sturgis Dam was the first municipal water power plant built in Michigan.[1] It is currently named after the city who owns it and paid for its construction. The dam is about 17 miles (27 km) away from the city of Sturgis which owns and operates the plant. The citizens of Sturgis passed a bond for a cost of $190,000 (equivalent to $4.61 million in 2023[2]) for the construction of the dam by a vote of 779 to 47.[3] Construction for the dam started in 1909 and the dam started producing power on September 3, 1911. Today the plant produces less than 4% of the city's electrical needs. It has been estimated that the city's operation of the plant has saved the city $56.6 million by reducing or eliminating the need to buy power from Indiana Michigan Power.[citation needed]

History

When the dam was being voted on local municipalities had just been given the right to use eminent domain for construction of projects like this. However, the use of eminent domain was not used to secure the necessary right. At the time there were no other dams upstream of the Sturgis Dam. The original design of the dam had four floors in the powerhouse. When first constructed, there was the 2,300-volt oil switches and 23,000-volt lightning arresters on the switchroom floor. The lowest floor held six 200-kW oil-cooled transformers. The original transmission line out was a 17-mile (27 km) three-phase line of No. 4 B & S hard drawn copper.[1] The bond that was approved was for $175,000 however the cost came to $250,000. When the dam was constructed it caused the Langley Covered Bridge to be raised eight feet (2.4 m).[citation needed]

The general contractor for the spillway and powerhouse was Carpenter & Anderson of Allis-Chalmers. The entire engineering work including preliminary surveys, and estimates was under the supervision of Gardner S. Williams of M. Am. Soc. C.E. Consulting engineer.

In 1930s the St. Joseph County Fish and Game Commission built two fish hatching ponds to stock the river. However, those ponds are now gone and overgrown.[citation needed]

In 1982 a second powerhouse was added with two Allis-Chalmers horizontal tube units.[citation needed]

During the 2011 Dam Days celebration a large boulder and plaque were placed on the grounds recognizing the dams centennial year of operation.[4]

Operation

See also