Supernova Spira

From Wikipedia, the free encyclopedia

StatusOn-hold
TypeMixed use
LocationNoida, India
Coordinates28°33′01″N 77°19′22″E / 28.5502°N 77.3228°E / 28.5502; 77.3228
Supernova Spira
Interactive map of the Supernova Spira area
General information
StatusOn-hold
TypeMixed use
LocationNoida, India
Coordinates28°33′01″N 77°19′22″E / 28.5502°N 77.3228°E / 28.5502; 77.3228
Construction started2012
OwnerSupertech
Height
Roof300 metres (980 ft) (proposed)
Technical details
Floor count68 (actual)
80 (proposed)
Lifts/elevators37
Design and construction
ArchitectBenoy
DeveloperSupertech
Website
Official website Edit this at Wikidata

Supernova Spira is an under construction mixed-use skyscraper in Noida, Uttar Pradesh, India being developed by Supertech.[1] It is located in Sector 94, Amrapali Marg, Noida.

The building was originally designed to stand 300 metres (984 ft) tall with 80 floors and would have been the tallest building in India outside of Mumbai.[2] However, due to significant construction delays stemming from the COVID-19 pandemic and financial challenges, the plans were subsequently revised.[3] The updated design now comprises 68 floors, following the removal of several elements from the original blueprint—most notably, the extruding helipad and the tapering building facade at the top of the structure.[4][5][6]

Upon completion, it will become the tallest building in Delhi-NCR.

  • 2012: Construction started.[7]
  • January 2016: Construction of 38 floors is completed.[citation needed]
  • June 2017: The structure crosses 180 metres (591 ft) in height with around 48 floors.[8]
  • August 2018: Construction reaches the 59th floor. Managing Director of Supertech Limited announces proposed completion by 2020.[9]
  • April 2020: Construction paused due to the COVID-19 pandemic.
  • September 2020: Uttar Pradesh Real Estate Regulatory Authority (UP-RERA) initiates investigations into financial irregularities related to the Supernova Spira project. Construction is put on hold indefinitiely.[10]
  • June 2024: Insolvency proceedings initiated against Supertech Supernova. Project continues to remain on hold, with 60% of the construction complete and 68 floors having been built.[4][3]
  • August 2024: Kotak Investments takes over the Supernova Spira project.[11]

As of October 2025, the project is still on hold and there is no active construction work ongoing at the project.