Tianwan Nuclear Power Plant is a nuclear power plant (NPP) on the coast of the Yellow Sea, approximately 30 kilometers east of downtown Lianyungang, Jiangsu Province, China. The plant's owner is Jiangsu Nuclear Power Corporation, a joint venture with majority owner a subsidiary of China National Nuclear Corporation (CNNC).

CountryChina
Coordinates34°41′13″N 119°27′35″E
StatusOperating / Under construction
Constructionbegan1999
Quick facts Tianwan Nuclear Power Plant 田湾核电站, Country ...
Tianwan Nuclear Power Plant
田湾核电站
Units one and two in operation, with the construction site for units three and four
CountryChina
Coordinates34°41′13″N 119°27′35″E
StatusOperating / Under construction
Construction began1999
Commission dateMay 17, 2006
Construction costUnit 1 & 2: Over $3.2 billion [1] Unit 3 & 4: $6 billion (Estimated) [2]
OwnerJiangsu Nuclear Power Corporation
Nuclear power station
Reactor typePWR
Reactor supplierAtomstroyexport
Power generation
Units operational2 × 990 MW VVER-1000/428 (AES-91)
2 × 1060 MW VVER-1000/428M
2 × 1000 MW ACPR-1000
Units under const.2 × 1171 MW VVER-1200
Nameplate capacity6,608 MWe
(6,100 MWe net)
External links
CommonsRelated media on Commons
Close
SimplifiedChinese田湾核电站
TraditionalChinese田灣核電站
Hanyu PinyinTiánwān Hédiànzhàn
Hanyu PinyinTiánwān Hédiànzhàn
Quick facts Simplified Chinese, Traditional Chinese ...
Tianwan Nuclear Power Plant
Simplified Chinese田湾核电站
Traditional Chinese田灣核電站
Hanyu PinyinTiánwān Hédiànzhàn
Transcriptions
Standard Mandarin
Hanyu PinyinTiánwān Hédiànzhàn
Close

The plant is planned to have eight Soviet/Russian VVER-type reactor units, and full operation is expected to commence in 2027. Construction began in October 1999, and was the first instance of civilian nuclear cooperation between Russia and China. When all the units are complete, Tianwan will be the world's largest nuclear power plant, with generation capacity exceeding 9,000 MWe.

Design

The station has four levels of security. There's a double asbestos cluster, which blocks any kind of emissions. Also there's a revolutionary security improvement called the trap, which prevents any leakage of nuclear fuel in the event of a breakdown

Alexandr Selikhov, head of Atomstroyexport's delegation to China

Most units use VVER pressurized water reactor (PWR) technology supplied from Russia. The first four units are Russian standard reactors of type VVER-1000, and have capacity approximately 1 GW. Units 5 and 6 are Chinese-designed ACPR-1000 reactors, with a traditional 3-loop system. Units 7 and 8 will use the updated VVER-1200 design capable of approximately 1.2 GW, with twice the expected operational lifetime and a 2/3-slower refueling cadence.[3][4]

The reactor units are housed in a confinement shell that can withstand a 20-ton aircraft crash, and have special earthquake protections.[citation needed] Other important safety features include an emergency "core catcher" in case of meltdown.[3]

The reactor and turbo-generators are of Russian design, but an international consortium, including Siemens, designed and built the control room. Previous control-room designs had not conformed to Western safety standards. A normal staffing load includes 5 control-room operators, but 94% of the systems are automated, and, in most circumstances, the plant could safely operate unattended. Refueling procedures, in particular, require little human intervention.

When complete, the plant's nameplate capacity will exceed 8000 MW.[5] This will make it the world's largest nuclear plant, surpassing both the active Kori NPP (7,411 MWe) and the inactive Kashiwazaki-Kariwa NPP (7,965 MWe).

Reactors

The Tianwan nuclear power plant has six operating units and two under construction:[6]

More information Unit, Reactor type ...
Unit Reactor type Capacity (MW) Construction Criticality Grid intertie Commercial
operations
Net Gross Thermal Start Contractor
1 VVER-1000/428 (AES-91) 99010603000 1999-10-20 Atomstroyexport (ASE)2005-12-202006-05-122007-05-17
2 VVER-1000/428 99010603000 2000-10-20 ASE2007-05-012007-05-142007-08-16
3 VVER-1000/428M 106011263000 2012-12-27 ASE & CNPE2017-09-292017-12-302018-02-14
4 VVER-1000/428M 106011263000 2013-09-27 ASE & CNPE2018-09-302018-10-272018-12-22
5 ACPR-1000 100011182905 2015-12-27 China Nuclear Power Engineering, Ltd. (CNPE)2020-07-272020-08-082020-09-08
6 ACPR-1000 100011182905 2016-09-07 CNPE2021-05-042021-05-112021-06-03
7 VVER-1200 117112653212 2021-05-19 2026 (planned)
8VVER-1200 117112653212 2022-02-25 2027 (planned)
Close

History

The Tianwan reactor's genesis is a 1992 nuclear cooperation agreement between Russia and China.[3] Regulators approved the initial design in 1997, and construction commenced on unit 1 in 1999 and a year later on Unit 2.[3] At the time, it was the largest reactor project of that design, and initial construction was slow. Corrosion in steam pipes delayed completion, but unit 1 went critical in 2005, and both units 1 and 2 entered commercial operation in 2007.[4] Russia delivered initial fuel loads for the Tianwan reactors, but China planned to begin indigenous fuel fabrication for the Tianwan plant in 2010, using technology transferred from Russian manufacturer TVEL.[7]

One year earlier (2009), Jiangsu Nuclear Power Corporation signed a contract with Atomstroyexport (ASE) for units 3 and 4,[3] but the 2011 Fukushima nuclear disaster delayed the start of construction for unit 3 until the end of 2012.[4][8] Construction of unit 4 would begin about a year later,[9][10] and the development cadence became quite swift. In 2015 and 2016, China National Nuclear Corporation (CNNC) started construction of units 5 and 6 (respectively).[4][11][12] In 2017, unit 3 achieved criticality,[3][8] and both units 3 and 4 started commercial operation in 2018.[3][9]

Units 3 and 4 initially remained owned by ASE, but in March 2019, CNNC contracted with ASE for units 7 and 8.[5][13] The following January, ASE transferred control of units 3 and 4 to Jiangsu Nuclear Power Corporation.[14]

Later in 2020, unit 5 achieved criticality and then entered commercial operation.[12][15] Construction of unit 7 began in May 2021[16] and then unit 6 entered commercial operation in June 2021.[11][17] Unit 8 began construction in 2022[13][18] and commercial operation of units 7 and 8 is expected to begin by 2027.[19]

Plant Ownership

The plant is owned by Jiangsu Nuclear Power Corporation (JNPC), a joint venture between China National Nuclear Power (50%), Shang Hai HeXi Power Investment (30%), and Jiangsu Guoxin Group (20%).[3]

Cost

The projected cost for Phase I of the project, which involved the first two VVER-1000/428 units, was initially set at $2.5 billion but ultimately exceeded $3.2 billion.[20] In comparison, the estimated cost for Phase II, which included the next two VVER-1000/428M units, was $6 billion.[20]

For units 1-4, the reactors are Rosatom products, but Atomstroyexport designed the units as a whole.[3]