Yadadri Thermal Power Plant

Thermal power project plant in India From Wikipedia, the free encyclopedia

Yadadri Thermal Power Plant is an operational 2400 megawatt, supercritical thermal power plant situated in Dameracherla, Nalgonda district in Telangana, India. Two more units of 800 MW each are under construction here .The project is second largest in South India[2], at a cost of ₹25,099 crores (US$3.8 billion) and was earlier expected to complete by October 2021 in a phased manner. The state-owned Telangana Power Generation Corporation Limited (TGGENCO) is operating the current 3x 800 mega thermal power station, built on 2800 acres near Veerlapalem Village in Nalgonda District, the second mega project announced by the Telangana government after Bhadradri Thermal Power Plant.

Official nameYadadri TPS
CountryIndia
LocationDameracherla, Nalgonda district, Telangana
Coordinates16°42′25″N 79°34′44″E
Quick facts Official name, Country ...
Yadadri Thermal Power Plant
Official nameYadadri TPS
CountryIndia
LocationDameracherla, Nalgonda district, Telangana
Coordinates16°42′25″N 79°34′44″E
Statusoperational[1]
Construction beganOctober 2017
Construction cost₹25,099 Crores
(USD $3.8 billion)
Owner TGGENCO
OperatorTGGENCO
Thermal power station
Primary fuelCoal
Power generation
Nameplate capacity4000 MW
External links
Websitetggenco.com/TGGENCO/home.do;jsessionid=8EC63E2115534D60C1EEAD4E13F1A383
Close

History

Chief Minister of Telangana, K. Chandrashekar Rao laid the foundation stone for the project on 8 June 2015 at Veerlapalem village, Dhamacherla mandal. The name was rechristened from Damaracharla Thermal Power Plant as Yadadri.

The Project

The BHEL order, the largest ever in India for the company,[3] includes design, supply, erection and commissioning of project on EPC basis. The project completion is executed on fast track basis within 36 months for first two units and balance three units in 48 months from October 2017.[4][5] This is the biggest project executed by BHEL.[6]

Clearances

The project has been accorded environmental clearance by the Ministry of Environment, Forest and Climate Change (MoEF&CC)in June 2017 [7] and yet to get water allocation from the Krishna River.[8]

MoEF granted Environment clearance to this thermal power plant on June 29, 2017.[9] LOI issued to BHEL with zero date 17 October 2017. The revised environment norms at the center, the 4000 MW project will cost Telangana an additional ₹3100 crore. The new environment norms mandate setting-up of flue-gas desulfurization (FGD) devices.

Capacity

The planned capacity of the thermal power plant is 4000 MW (5 × 800 MW)

More information Stage, Unit Number ...
StageUnit NumberInstalled Capacity (MW)Date of CommissioningStatus
Stage IUnit I800 MW31 Dec 2023operational [10]
Stage IUnit II800 MW31 Dec 2023operational
Stage IIUnit III800 MW30 June 2024operational
Stage IIUnit IV800 MW30 June 2024work commenced
Stage IIUnit V800 MW30 June 2024work commenced