Yakov Novichenko Bridge
Bridge in Khasan, Tumangang
From Wikipedia, the free encyclopedia
The Khasan–Tumangang Bridge (Russian: Автомобильный мост между Приморьем и КНДР, Korean: 프리모리예와 조선을 잇는 자동차 다리) is an international road bridge across the Tumen River on the North Korea–Russia border, currently under construction. The crossing will connect Khasan, Russia and Tumangang, North Korea. When complete, the bridge will supplement the existing Korea–Russia Friendship Bridge through providing a road transit link between the cities of Vladivostok and Chongjin. It is sited approximately 15km upstream from the river's mouth at the Sea of Japan, and approximately 1km downstream from the limit of extent of Chinese territory down the Tumen River.
Yakov Novichenko Bridge | |
|---|---|
Site of the future bridge, located to the east of the Korea–Russia Friendship Bridge | |
| Coordinates | 42.412022°N 130.645833°E |
| Crosses | Tumen River, North Korea–Russia border |
| Locale | Khasan, Tumangang |
| Characteristics | |
| Design | Girder bridge |
| Total length | 1.005 km (0.6 mi) |
| Width | 7 m (23 ft) |
| No. of lanes | 2 |
| History | |
| Constructed by | TunnelYuzhStroy |
| Construction start | 30 April 2025 |
| Construction end | Summer 2026 (expected) |
| Construction cost | ₽9 billion (expected) |
| Location | |
![]() Interactive map of Yakov Novichenko Bridge | |
History
Since August 1959, the sole crossing point between the Russia and North Korea has been the Korea–Russia Friendship Bridge.[1] Planks are laid between the tracks, making the crossing of road vehicles possible by special arrangement, but it is primarily a rail bridge.[2] Logistics are further complicated by the North Korean railway network primarily using standard-gauge railways, with the Russian gauge line terminating at the port city of Rason.
Design
The bridge spans the Tumen River and is located 415 meters to the east of the existing Korea-Russia Friendship Bridge.[3] The bridge is supported by concrete supports and steel spans of a distance of 1,005 meters, with 581 meters on the North Korean side and 424 meters on the Russian side.[4] The road deck contains two lanes with a width of seven meters.[5] On the Russian side, a 2.4 km road around Khasan would also be built. Border checkpoints are also to be established on both sides of the bridge.
Once operational, the Khasan border checkpoint is designed to process up to 300 vehicles per day.[6]
The cost of construction is estimated to be approximately 9 billion rubles.[6] In 2025, 120 million rubles for design and 5.38 billion rubles for construction were allocated from the federal budget. The remaining 3.57 billion rubles is planned for 2026.
Construction

In early 2025, the tender for construction work on the Russian side was awarded to the Sochi based TunnelYuzhStroy.[7] In addition preparatory work began on the Tumangang side in early 2025.[8]
Construction work on the bridge began on 30 April 2025, following a virtual announcement by Russian prime minister Mikhail Mishustin and Premier of North Korea, Pak Thae-song.[5][9][6][10] Russian sources indicated that the target completion date was set for December 2026.[4]
Speaking at the 2025 Eastern Economic Forum in September 2025, Russian President Vladimir Putin clarified that the bridge would be completed in 2026.[11]
By October 2025, construction had progressed significantly, with a new aggregate plant, border checkpoint, access road and support piers progressing on the North Korean side.[12] On the Russian side, support piers, access roads and a helipad were underway.[13][14]
In early January 2026, Russian media reported that the bridge was expected to be complete by 19 June 2026.[15]
By mid-March 2026, both Korean and Russian bridge spans were close to being connected, spanning the width of the Tumen River.[16] Satellite imagery showed that progress on border infrastructure and connecting roads on both sides of the river had also progressed.[17][18]
In April 2026, Russian transport minister Andrei Nikitin and his North Korean counterpart Cho Jong-ryong reported at the International Transport and Logistics Forum in Saint Petersburg that construction was proceeding according to schedule, with an expected opening in Summer 2026.[19][20] On 21 April 2026, a ceremony marking the connection of both sides of the bridge was held.[21][22][23]
By June 2026, significant progress had been made in the construction of buildings at the Russian customs area and by early August, satellite imagery showed the exterior nearing completion.[24]
In late August 2026, Russian officials reported that the construction of border infrastructure continued to progress.[25][26] Images of the bridge and border checkpoint facilities under construction were shared, showing several buildings in a state of near completion, as well as the now paved road deck. Satellite imagery confirmed this progress, showing paving works underway to connect the bridge to the existing highway in Khasan.[27][25] It was further reported that the Sochi based contractor TonnelYuzhStroi was facing a lawsuit from Primorskaya Nerudnaya, a supplier of rock soil for the project.[28] In September 2026 it was reported that costs further increased due to the addition of canpoies worth of $6 million USD according to information published by Rosgranstroy firm via a state procurement portal.[29]