Rishikesh–Karnaprayag line

Railway under construction in India From Wikipedia, the free encyclopedia

The Rishikesh–Karnaprayag line is a 126 km long under-construction railway line, connecting Yog Nagari Rishikesh railway station in Rishikesh city in the Himalayan foothills Sivalik Hills to Karnaprayag city in the Garhwal region in Lower Himalayan Range of Uttarakhand state of India. It is the main feeder route to Indian Railways' Char Dham Railway project which aims to connect the Char Dham pilgrimage shrines of Yamunotri, Gangotri, Badrinath and Kedarnath. As part of an Indian geostrategic initiative to build infrastructure along the India-China border to discourage Chinese expansion, this rail line is of national strategic importance,[1][2][3] which will cut down the travel time to 2 and half hours by railway from earlier 8 hours taken by the road.[4]

StatusUnder construction
Termini
Quick facts Overview, Status ...
Rishikesh–Karnaprayag line
Overview
StatusUnder construction
OwnerRail Vikas Nigam
LocaleUttarakhand
Termini
Stations12
Websitehttp://www.indianrailways.gov.in
Service
SystemBroad gauge
ServicesSingle track
Operator(s)Indian Railways
Technical
Line length126 km (78 mi)
Track length126 km (78 mi)
Track gauge1,676 mm (5 ft 6 in)
Minimum radius440 m (1,440 ft)
Electrification25 kV 50 Hz AC OHE
Operating speed100 km/h (62 mph)
Highest elevation1,451 m (4,760 ft)
Route map

0
Karnaprayag
9
Ghauchar
15
Gholtir
28
Rudraprayag
37
Dhari
51
Srinagar Garhwal
56
Kirtinagar
78
Devaprayag
93
Sakni
105
Manjilgaon
112
Shivpuri
Chandrabhaga River
130
Yog Nagari Rishikesh
to Laksar–Dehradun line
Close

History

Satpal Maharaj began a survey for the project as Minister of Railways of Uttarakhand in 1996.[5][6][7]

The project's foundation stone was scheduled to be laid by United Progressive Alliance chairperson Sonia Gandhi on 9 November 2011. [8] Alignment of the 126-kilometer-long railway project was completed in 2013,[9] but the project was delayed by political wrangling.[10]

The detailed feasibility work finally began in 2015 under the leadership of Narendra Modi led National Democratic Alliance government. Design contracts for tunnel and bridge construction were awarded in 2019. Italferr, the engineering arm of FS Italiane Group, received the contract for the design and supervision of the 12-km-long section (running almost entirely through tunnels) of the Himalaya Tunnel as part of a joint venture with Swiss firm Lombardi SA.[11] That construction began in 2018. Work on the first block section, from the Virbhadra railway station to Yog Nagari Rishikesh, began in June 2018 and was completed in 2020.

Strategic importance

It will play a vital role in national security and the welfare of Uttarakhand,[12] by reducing travel time between Rishikesh and Karnaprayag from 6-7 hours to 2+12 hours.[13] The line will serve pilgrims and local residents, and will be able to rapidly move troops to the India-China border.[14]

Project features

This 16,200 crore (US$1.7 billion) project, with 35 bridges, and 105 km (85 percent) will run through 17 tunnels including 15.1-km Devprayag-Lachmoli tunnel which was reportedly India's longest tunnel in 2016.[13]

Route

The Rishikesh–Karnaprayag line, which begins at Yog Nagari Rishikesh station (385 m ) and ends at Karnaprayag station (825 m ) city,[13] will have the following 12 stations (sequentially listed southwest to northwest direction) all of which are in Uttarakhand state.

  • Tehri Garhwal district
    • Manjilgaon
    • Sakni
    • Devprayag
    • Kirtinagar
  • Pauri Garhwal district
    • Srinagar
    • Dungripanth (Dhari devi)
  • Char Dham Highway: will complement the Rishikesh–Karnaprayag line mostly along the same route
  • Parvatmala, ropeway project across India, including ropeways in some of the destinations of the Rishikesh–Karnaprayag line

Status

  • 2024 Nov: 60% of the project's budget has been utilised with 70% work completed, with 28 of the 38 planned tunnel breakthroughs completed, and the remaining 10 are scheduled for breakthroughs by March 2025, 11 stations were under-construction.[15][3][16]
  • 2025 Nov: 201 km tunneling work out of 213 completed. The earlier project completion date of December 2026 has been revised to more realistic completion date of December 2028.[17]
  • 2025 Dec:76 % physical work completed with 69% budget spent (Rs 26,841 crore out of the total estimated Rs 38,953 crore project cost).[18]