Thorntonbank Wind Farm

Belgian offshore wind farm in the North Sea From Wikipedia, the free encyclopedia

The Thorntonbank Wind Farm (also known as C-Power) is an offshore wind farm. It is the first offshore wind farm in Belgium.

Country
  • Belgium
Location28 km north off the Belgian coast
Coordinates51°33′06″N 2°58′01″E
StatusOperational
Quick facts Country, Location ...
Thorntonbank Wind Farm
Wind turbines D4 (nearest) to D1 on the Thornton Bank
Country
  • Belgium
Location28 km north off the Belgian coast
Coordinates51°33′06″N 2°58′01″E
StatusOperational
Construction began
  • February 2008
Commission date
  • 18 September 2013
Construction cost€ 1.3 billion
Wind farm
Type
Max. water depth
  • 28 m (92 ft)
Distance from shore
  • 27 km (17 mi)
Rotor diameter
  • 126 m (413 ft)
Site area
  • 19.84 km2 (7.66 sq mi)
Power generation
Units operational6 × 5 MW
48 × 6.15 MW
Make and modelSenvion 6.2M126 (48)
Senvion REpower 5M (6)
Nameplate capacity
  • 325 MW
External links
Websitec-power.be
CommonsRelated media on Commons
Close

Electricity production started in early 2009, with a capacity of 30 MW. The capacity was increased to a total of 214 MW in 2012 and 325 MW in 2013.[1]

Phases

Wind farm layout

First phase

The first phase was built by C-Power, at a cost of 153 million.[2] It was commissioned in June 2009.[3][4]

The first phase of what will ultimately be a 325 MW wind farm was completed in September 2008. The six REpower 5 MW turbines, which were installed on concrete gravity foundations, were linked to the Belgian power grid, giving a total rated capacity of 30 MW for the first stage.[5] The full story of the design, engineering, construction and installation of the Thorntonbank Wind Farm (first phase) is told in an illustrated book that was published in November 2010.[6][7]

Second and third phase

In these phases, a total of 48 additional wind turbines of 6.15MWp were installed.[8]

Phase 2, completed in October 2012, comprises the installation of 30 of the 48 wind turbines.[1] These wind turbines have been installed on steel jacket foundations designed by OWEC Tower AS and assembled at the Smulders shipyard in Hoboken, Antwerp.[9]

In the third and last phase, completed in September 2013, the remaining 18 wind turbines were installed, bringing the total capacity to around 325 MW.[1][10]

Environmental assessment

Research was by the Research Institute for Nature and Forest (INBO[11]) and the Institute for Agricultural and Fisheries Research (ILVO [12])

Financing

Thorntonbank was only the second offshore wind farm to be project financed.[13]

See also

References

Related Articles

Wikiwand AI