Thorntonbank Wind Farm
Belgian offshore wind farm in the North Sea
From Wikipedia, the free encyclopedia
The Thorntonbank Wind Farm (also known as C-Power) is an offshore wind farm. It is the first offshore wind farm in Belgium.
- Belgium
| Thorntonbank Wind Farm | |
|---|---|
Wind turbines D4 (nearest) to D1 on the Thornton Bank | |
![]() | |
| Country |
|
| Location | 28 km north off the Belgian coast |
| Coordinates | 51°33′06″N 2°58′01″E |
| Status | Operational |
| Construction began |
|
| Commission date |
|
| Construction cost | € 1.3 billion |
| Wind farm | |
| Type | |
| Max. water depth |
|
| Distance from shore |
|
| Rotor diameter |
|
| Site area |
|
| Power generation | |
| Units operational | 6 × 5 MW 48 × 6.15 MW |
| Make and model | Senvion 6.2M126 (48) Senvion REpower 5M (6) |
| Nameplate capacity |
|
| External links | |
| Website | c-power |
| Commons | Related media on Commons |
Electricity production started in early 2009, with a capacity of 30 MW. The capacity was increased to a total of 214 MW in 2012 and 325 MW in 2013.[1]
Phases
First phase
The first phase was built by C-Power, at a cost of €153 million.[2] It was commissioned in June 2009.[3][4]
The first phase of what will ultimately be a 325 MW wind farm was completed in September 2008. The six REpower 5 MW turbines, which were installed on concrete gravity foundations, were linked to the Belgian power grid, giving a total rated capacity of 30 MW for the first stage.[5] The full story of the design, engineering, construction and installation of the Thorntonbank Wind Farm (first phase) is told in an illustrated book that was published in November 2010.[6][7]
Second and third phase
In these phases, a total of 48 additional wind turbines of 6.15MWp were installed.[8]
Phase 2, completed in October 2012, comprises the installation of 30 of the 48 wind turbines.[1] These wind turbines have been installed on steel jacket foundations designed by OWEC Tower AS and assembled at the Smulders shipyard in Hoboken, Antwerp.[9]
In the third and last phase, completed in September 2013, the remaining 18 wind turbines were installed, bringing the total capacity to around 325 MW.[1][10]
Environmental assessment
Financing
Thorntonbank was only the second offshore wind farm to be project financed.[13]
Gallery
- Wind turbine D1
- Wind turbines D1 to D6
- Wind turbine bases under construction
- Wind turbine bases under construction
- As seen from the Belgian coast, demonstrating the curvature of the Earth; the more distant windmills look to be underwater

