This is a list of Mass Rapid Transit (MRT) lines in Singapore, with details on costs, construction timelines and route length.

North–South Line

More information Stage, Date ...
Stage Date Length Stretch Stations Cost
Commencement
of construction
Service commencement Names Codes Elevated At-grade Underground
ContemporaryRetired
Phase 1 22 October 1983; 42 years ago (1983-10-22) 7 November 1987; 38 years ago (1987-11-07) 6 km[1] Yio Chu Kang - Toa Payoh NS15 - NS19 N10 - N6 2
(40%)
1
(20%)
2
(40%)
S$5 billion[a]
12 December 1987; 38 years ago (1987-12-12) 7 Toa Payoh - Raffles Place NS19 - NS26 N6 - C1 N/a N/a 7
(100%)
Phase 2B June 1985; 41 years ago (1985-06) 20 December 1988; 37 years ago (1988-12-20) TBD Yio Chu Kang - Yishun NS15 - NS13 N10 - N12 2
(100%)
N/a
Phase 2A January 1985; 41 years ago (1985-01) 4 November 1989; 36 years ago (1989-11-04) TBD Raffles Place - Marina Bay NS26 - NS27 C1 - M1 N/a 1
(100%)
Phase 2B
(Branch Line)
June 1985; 41 years ago (1985-06) 10 March 1990; 36 years ago (1990-03-10) 6.5 km Jurong East - Choa Chu Kang NS1 - NS4 W9 - B3;
W9, N23 - N21
3
(100%)
N/a
Woodlands Extension TBD 10 February 1996; 30 years ago (1996-02-10) 16 km Choa Chu Kang - Yishun NS4 - NS13 N21 - N12 6
(100%)
S$1.2 billion[2]
North–South Line Extension December 2009; 16 years ago (2009-12)[3] 23 November 2014; 11 years ago (2014-11-23) 1 km Marina Bay - Marina South Pier NS27 - NS28 N/a N/a 1
(100%)
S$357.5 million[3]
Canberra station (infill) 26 March 2016; 10 years ago (2016-03-26)[4] 2 November 2019; 6 years ago (2019-11-02) N/a Canberra NS12 1
(100%)
N/a S$274 million[5]
Brickland station (infill) H1 2026 2034; 8 years' time (2034) Brickland NS3A S$281 million[6]
Sungei Kadut station (infill) Q2 2026 2035; 9 years' time (2035) Sungei Kadut NS6 TBD
Total 45 km Jurong East - Marina South Pier NS1 - NS28 17
(59%)
1
(3%)
11
(38%)
S$11.95 billion[b]
29
(100%)
Close

East–West Line

More information Stage, Date ...
Stage Date Length Stretch Stations Cost
Commencement
of construction
Service commencement Names Codes Elevated Underground
ContemporaryRetired
Phase 1 22 October 1983; 42 years ago (1983-10-22) 12 December 1987; 38 years ago (1987-12-12) TBD Raffles Place - Outram Park EW14 - EW16 C1 - W2 N/a 2
(100%)
S$5 billion[a]
Phase 1A January 1984; 42 years ago (1984-01) 12 March 1988; 38 years ago (1988-03-12) TBD Outram Park - Clementi EW16 - EW23 W2 - W8 5
(83%)
1
(17%)
Phase 2B July 1984; 42 years ago (1984-07) 5 November 1988; 37 years ago (1988-11-05) TBD Clementi - Lakeside EW23 - EW26 W8 - W11 3
(100%)
N/a
Phase 2A January 1985; 41 years ago (1985-01) 4 November 1989; 36 years ago (1989-11-04) TBD City Hall - Tanah Merah EW13 - EW4 C2 - E9 7
(78%)
2
(22%)
June 1985; 41 years ago (1985-06) 16 December 1989; 36 years ago (1989-12-16) TBD Tanah Merah - Pasir Ris EW4 - EW1 E9 - E12 3
(100%)
N/a
Phase 2B January 1988; 38 years ago (1988-01) 6 July 1990; 36 years ago (1990-07-06) TBD Lakeside - Boon Lay EW26 - EW27 W11 - W12 1
(100%)
N/a
Changi Airport Extension TBD 10 January 2001; 25 years ago (2001-01-10) TBD Tanah Merah - Expo CG - CG1 E9, E13 N/a S$850 million[7]
TBD 8 February 2002; 24 years ago (2002-02-08) TBD Expo - Changi Airport CG1 - CG2 N/a N/a 1
(100%)
Dover station (infill) TBD 18 October 2001; 24 years ago (2001-10-18) N/a Dover EW22 N/a 1
(100%)
N/a S$45 million[8]
Boon Lay Extension TBD 28 February 2009; 17 years ago (2009-02-28) 3.8 km Boon Lay - Joo Koon EW27 - EW29 N/a 2
(100%)
N/a S$436 million[9]
Tuas West Extension TBD 18 June 2017; 9 years ago (2017-06-18) 7.5 km Joo Koon - Tuas Link EW29 - EW33 N/a 4
(100%)
N/a S$3.5 billion[10]
Total 56.7 km Pasir Ris - Tuas Link
Tanah Merah - Changi Airport
EW1 - EW33
CG - CG2
27
(77%)
8
(23%)
S$11.95 billion[b]
35
(100%)
Close

North East Line

More information Stage, Date ...
Stage Date Length Stretch Stations Cost
Commencement
of construction
Service commencement Names Codes
N/a 25 November 1997; 28 years ago (1997-11-25) 20 June 2003; 23 years ago (2003-06-20) 20 km HarbourFront - Punggol NE1
NE3 - NE10
NE12 - NE14
NE16 - NE17
14 S$4.6 billion
Buangkok station 15 January 2006; 20 years ago (2006-01-15) Buangkok NE15 1 TBD
Woodleigh station 20 June 2011; 15 years ago (2011-06-20) Woodleigh NE11 TBD
North East Line Extension TBD 10 December 2024; 19 months ago (2024-12-10) 1.6 km Punggol - Punggol Coast NE17 - NE18 S$79 million[11]
Total 21.6 km HarbourFront - Punggol Coast NE1 - NE18 17 S$5.39 billion[c]
Close

Circle Line

More information Stage, Date ...
Stage Date Length Stretch Stations Cost
Commencement
of construction
Service commencement Names Codes
ContemporaryRetired
Stage 3 May 2003; 23 years ago (2003-05) 28 May 2009; 17 years ago (2009-05-28) 5.7 km[12] Bartley - Marymount CC12 - CC16 N/a 5 S$10 billion
Stage 2 5 September 2002; 23 years ago (2002-09-05) 17 April 2010; 16 years ago (2010-04-17) 5.5 km[13][12] Bartley - Mountbatten CC12 - CC7
Stage 1 5 March 2002; 24 years ago (2002-03-05) 5.5 km[12] Mountbatten - Dhoby Ghaut CC7 - CC1 6
Stage 4 January 2005; 21 years ago (2005-01) 8 October 2011; 14 years ago (2011-10-08) 9.8 km Marymount - Kent Ridge CC16 - CC17
CC19 - CC24
7
Stage 5 6.8 km Kent Ridge - HarbourFront CC24 - CC29 5
Circle Line Extension November 2007; 18 years ago (2007-11)[14] 14 January 2012; 14 years ago (2012-01-14) 2.4 km Promenade - Marina Bay CC4 - CC33 CC4 - CE2 2 S$811.4 million[15][unreliable source?][d]
Stage 6 2017; 9 years ago (2017)[16] 12 July 2026; 22 days ago (2026-07-12) 4.0 km HarbourFront - Marina Bay CC29 - CC33 CC29 - CE2 3 S$4.85 billion[17]
Bukit Brown station (infill) TBD TBD N/a Bukit Brown CC18 N/a 1 TBD
Total 39.7 km Dhoby Ghaut - Bayfront
CC1 - CC34 34 S$15.67 billion[e]
Close

Downtown Line

More information Stage, Date ...
Stage Date Length Stretch Stations Cost
Commencement
of construction
Service commencement Names Codes
Stage 1 TBD 22 December 2013; 12 years ago (2013-12-22) 4.3 km Bugis - Chinatown DT14 - DT19 6 TBD
Stage 2 3 July 2009; 17 years ago (2009-07-03) 27 December 2015; 10 years ago (2015-12-27) 16.6 km Bugis - Bukit Panjang DT14 - DT5
DT3 - DT1
12 TBD
Stage 3 TBD 21 October 2017; 8 years ago (2017-10-21) 21.0 km Chinatown - Expo DT19 - DT35 16 TBD
Hume station (infill) 28 February 2021; 5 years ago (2021-02-28) 28 February 2025; 17 months ago (2025-02-28) N/a Hume DT4 1 S$259.5 million
Stage 3 Extension 21 July 2016; 10 years ago (2016-07-21)[18] 2026; 0 years ago (2026) 2.2 km Expo - Sungei Bedok DT35 - DT37 2 TBD
Stage 2 Extension Q2 2026 2035; 9 years' time (2035) 4.0 km Bukit Panjang - Sungei Kadut DT1 - DE2 2 S$1.26 billion[19]
Total 48.1 km Sungei Kadut - Sungei Bedok DE2 - DT37 39 TBD
Close

Thomson–East Coast Line

More information Stage, Date ...
Stage Date Length Stretch Stations Cost
Commencement
of construction
Service commencement Names Codes Elevated Underground
ContemporaryRetired
Stage 1 27 June 2014; 12 years ago (2014-06-27)[20] 31 January 2020; 6 years ago (2020-01-31) 2.9 km Woodlands North - Woodlands South TE1 - TE3 N/a N/a 3
(100%)
TBD
Stage 2 28 August 2021; 4 years ago (2021-08-28) 11.4 km Woodlands South - Caldecott TE3 - TE9 N/a N/a 6
(100%)
TBD
Stage 3 13 November 2022; 3 years ago (2022-11-13) 13.5 km Caldecott - Gardens by the Bay TE9
TE11 - TE20
TE22
N/a N/a 11
(100%)
TBD
Mount Pleasant station (infill) TBD Mount Pleasant TE10 N/a N/a 1
(100%)
TBD
Marina South station (infill) TBD Marina South TE21 N/a N/a TBD
Stage 4 21 July 2016; 10 years ago (2016-07-21)[18] 23 June 2024; 2 years ago (2024-06-23) 10.1 km Gardens by the Bay - Bayshore TE22 - TE29 N/a N/a 7
(100%)
TBD
Stage 5 2026; 0 years ago (2026) 2.5 km Bayshore - Sungei Bedok TE29 - TE31 N/a N/a 2
(100%)
TBD
Founders' Memorial station (infill) 2028; 2 years' time (2028) N/a Founders' Memorial TE22A N/a N/a 1
(100%)
TBD
Thomson–East Coast Line Extension TBD mid-2030s 14.0 km Sungei Bedok - Tanah Merah TE31 - TE35 TE31 - CG 2
(50%)
TBD
Tagore station (infill) TBD TBD N/a Tagore TE4A N/a N/a 1
(100%)
TBD
Total 57 km Woodlands North - Tanah Merah TE1 - TE31 2
(5%)
35
(95%)
TBD
37
(100%)
Close

Jurong Region Line

More information Stage, Date ...
Stage Date Length Stretch Stations Cost
Commencement
of construction
Service commencement Names Codes
Stage 1 13 January 2023; 3 years ago (2023-01-13)[21] mid-2028; 2 years' time (2028) 24 km Choa Chu Kang - Boon Lay
Bahar Junction - Tawas
JS1 - JS8
JS7 - JW2
10 TBD
Stage 2 2028; 2 years' time (2028) Tengah - Pandan Reservoir JS3 - JE7 7 TBD
Stage 3 2029; 3 years' time (2029) Boon Lay - Jurong Pier
Tawas - Peng Kang Hill
JS8 - JS12
JW2 - JW5
TBD
JS2A station (infill) TBD mid-2030s N/a JS2A JS2A 1 TBD
West Coast Extension Phase 1 TBD late-2030s TBD Pandan Reservoir - West Coast JE7 - JE? TBD TBD
West Coast Extension Phase 2 TBD early-2040s TBD West Coast - Kent Ridge JE? - JE? TBD TBD
Total 24 km Choa Chu Kang - Jurong Pier
Tengah Plantation - Pandan Reservoir
Gek Poh - Peng Kang Hill
JS1 - JS12
JE1 - JE7
JW1 - JW5
27 TBD
Close

Cross Island Line

More information Stage, Date ...
Stage Date Length Stretch Stations Cost
Commencement
of construction
Service commencement Names Codes
Phase 1 18 January 2023; 3 years ago (2023-01-18)[22] 2030; 4 years' time (2030) 29.0 km Aviation Park - Bright Hill CR2 - CR13 12 S$7.64 billion[f]
Punggol Extension 10 October 2023; 2 years ago (2023-10-10)[23] 2032; 6 years' time (2032) 7.3 km Pasir Ris - Punggol CP1 - CP4 3 S$2.16 billion[f][g]
Phase 2 7 July 2025; 12 months ago (2025-07-07)[24] 15.0 km Bright Hill - Jurong Lake District CR13 - CR19 6 S$3.51 billion[f]
Changi Airport extension TBD mid-2030s 5.8 km Aviation Park - Changi Terminal 5 CR2 - CR1 1 TBD
Phase 3 2027 late-2030s 10.0 km Jurong Lake District - Gul Circle CR19 - CR23 4 TBD
Total 67 km Changi Terminal 5 - Gul Circle
Pasir Ris - Punggol
CR1 - CR23
CP1 - CP4
26 S$13.31 billion[h]
Close

See also

Notes

  1. Total cost of Phase 1 and 2 of the North–South Line and East–West Line.
  2. Total cost of the North–South Line and East–West Line.
  3. Not inclusive of Buangkok and Woodleigh stations.
  4. S$348.4 million for Marina Bay CCL station; $463 million for Bayfront CCL + DTL station.
  5. The cost breakdown of Stages 1-5 is not available.
  6. Refer to list of Cross Island Line stations for breakdown of cost of CRL.
  7. Excluding Pasir Ris station.
  8. Excluding Phase 3 and Changi T5 station.