Thane Metro

From Wikipedia, the free encyclopedia

Other nameThane Integral Ring Metro
StatusUnder Construction
LocaleThane, Maharashtra, India
Thane Metro
Overview
Other nameThane Integral Ring Metro
StatusUnder Construction
OwnerMaharashtra Metro Rail Corporation Limited
LocaleThane, Maharashtra, India
Connecting linesUpcoming (2):
Green Line 4 Orange Line 5
Stations22
Websitewww.thanemetrorail.com
Service
TypeMetro
Depot(s)Kasarvadavali
History
Planned opening2029; 3 years' time (2029)
Technical
Line length29 km (18 mi)
Number of tracks2
CharacterElevated & Underground
Track gauge1,435 mm (4 ft 8+12 in) standard gauge
Electrification750 V DC third rail

The Thane Metro or Thane Integral Ring Metro is an under-construction[1] rapid transit line serving Thane, Maharashtra. This metro line will be the third line to run across Thane City after the under construction Line 4 and Line 5 of Mumbai Metro. The line has an approved length of 29 km (18 mi) and 22 stations. Of the total length, 3 km (1.9 mi) along with 2 stations are approved to be underground while the remaining are to be elevated. Unlike other metro lines in Mumbai Metropolitan Region, the line forms a loop running from Thane Junction via Wagle Estate, Manpada, Waghbil, Balkum, and Rabodi, to Thane Railway Station.[2] The line was approved by the central government on 14 August 2024 and is expected to be operational by 2029.[3]


Proposal

The line was initially proposed by the Thane Municipal Corporation. It proposed a 29 km line running through core areas of Thane. Initially the TMC proposed the line as a heavy rail project. The initial draft was approved by the TMC in December 2018 after which it was submitted to the state government the next month. The state government approved the project on March 6.[4] However, following financial difficulties the line was put on hold. Later in December 2020, the TMC revised the line again with several modifications. Rather than a heavy rail system, the line was converted to a light rail to reduce costs, the coach count was reduced from 6 coaches per train set to 3 coaches.[5] This revised proposal received criticism from the public stating that a Light Rail Project would not be sufficient for a city like Thane. In 2023, however, TMC once again scrapped its proposal of a light rail system and revised the line to a Heavy rail again. The final draft saw a proposed interchange facility with the under construction Line 4 and Line 5 of Mumbai Metro.[6] It also proposed the line to go underground near the Thane Railway Station and CIDCO Bus Terminal. The line was finally approved by the central government on 14 August 2024 and by the state government on 30 September 2024 with an estimated cost of 12,200 crore (US$1.4 billion).[7][8] The project was initially supposed to be executed by the Thane Municipal Corporation. However, this was later modified when Maha Metro was assigned as the agency responsible for the implementation of the line.[9] Finally the foundation for the line was laid by Prime Minister Narendra Modi on 5 October 2024.[10][11][12][13]

Cost and Funding

The project is estimated to cost 12,200.10 crore (US$1.4 billion) with both the central and state governments expected to contribute with equal equity.[9][14]

Funding
Source Amount %
Equity by Central Government 1,151.13 crore (US$140 million) 9.51
Equity by State Government 1,151.13 crore (US$140 million) 9.51
Sub Debt by Central Government 354.11 crore (US$42 million) 2.92
Sub Debt by State Government 354.11 crore (US$42 million) 2.92
Contribution from Local Bodies 200 crore (US$24 million) 1.65
Sub Debt for land and R&R by State Government 3,414.20 crore (US$400 million) 28.22
State Taxes by State Government 615.64 crore (US$73 million) 5.08
Interest During Construction by State Government 312.71 crore (US$37 million) 2.58
Bilateral & Multilateral Loans 4,515.73 crore (US$530 million) 37.32
PPP Component 131.34 crore (US$16 million) 1.08
Total 12,100.10 crore (US$1.4 billion) 100

Construction

Tendering

Maha Metro has started the tendering process for the line following the approval from the Central and State government.[15]

Thane Metro
Pre Construction Activity
Tendering Section Activity Successful Bid / Cost Contractor Award
T-002/DDC-01/2024 Dr. Kashinath Ghanekar Natyagraha - Waterfront Detailed Design Consultant 1.35 crore (US$160,000) STUP Consultants 28 Oct 2024
T1-011/DDC-02/2025 Kasarvadavali Depot Detailed Design Consultant Bidding Underway
T1-024/DDC-03/2025 A) Architecture, Tunnel Ventilation System, Environmental Control System & Building Management System.

B) Thane Junction - New Thane (Underground Section including ramps)

Detailed Design Consultant Bidding Underway
T1-004/Consul-01/2024 General Consultant 142.03 crore (US$17 million) AECOM India 21 April 2026
T1-006/S&E-01/2024 Environmental Impact Assessment & Environmental Management Plan Bidding Underway
T1-007/S&E-02/2024 Social Impact Assessment & Rehabilitation & Resettlement (R&R Policy) Plan Bidding Underway
T1-018/RS-01/2025 Consultancy for Review & Interface Validation between Various systems with Regard to implementation of UTO Operations Bidding Underway
T1-019/Consul-05/2025 Engagement of General Consultants Bidding Underway
Total 143.38 crore (US$17 million)
Civil Work
Package Section Length Successful Bid / Cost Contractor Award
T1-015/C-01/2025 Viaduct from Raila Devi to Shivaji Chowk 20.527 km (12.755 mi) 1,415 crore (US$170 million) H.G. Infra & Kalpaturu JV 2 Dec 2025
T1-023/C-02/2025 Six Stations from Manpada to Patlipada Bidding Underway
T1-030/DDC-04 Six Stations from Raila Devi to Gandhi Nagar Bidding Underway
T1-030/DDC-05 Seven Stations from Azad Nagar Bus Stop to Shivaji Chowk Bidding Underway
TBD Underground Section Tenders to be invited
Total 1,415 crore (US$170 million)
Miscellaneous Work
Package Scope of work Successful Bid / Cost Contractor Award
T1-022/ELE-02/2025 Modification of 110 KV/220KV EHV M/C overhead lines at

A) Near Waghbil station and Kasarvadavali Depot B) 220KV EHV D/C overhead lines between Balkum Naka to Balkum Pada Station.

Bidding Underway
Total -
Total Cost 1,558.38 crore (US$180 million)

Stations

Infrastructure

References